GLDD wraps up Buxton beach nourishment project

EG

Eldin Ganic

Dredging Today

1 minutes read
photo courtesy of darenc.gov
photo courtesy of darenc.gov

Great Lakes Dredge & Dock Company (GLDD) said that the 2026 Buxton beach nourishment project has been completed, with the contractor delivering the final load of sand on Saturday, October 3, 2026.

Approximately 1.9 million cubic yards of sand was placed along the shoreline within the project area, providing increased protection for infrastructure and N.C. Highway 12. The only area that was not able to be nourished as originally planned was the northern taper, one of the least vulnerable areas of the project, Dare County said. 

The project was completed in 69 calendar days, despite an interruption caused by a powerful late-September nor’easter.

"The final volume of sand is just short of the contract amount because operations ended earlier than anticipated due to the incidental take of 10 sea turtles, reaching the limit established by the U.S. Army Corps of Engineers’ (USACE) special use permit. This occurred despite numerous protective measures in place to avoid impacts to turtles," the County said.

The decision to end work was made in close coordination with resource and regulatory agencies, including U.S. Fish & Wildlife Service and USACE. 

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Daily Dredging and Port Construction News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.