Preparing the Fehmarnbelt project basins for the shipping of tunnel elements

The world’s largest precast concrete element factory in Rødbyhavn, which is being used for the construction of the Fehmarnbelt tunnel elements, has taken another step towards shipping of the first tunnel element into the Fehmarnbelt.

Photo courtesy of Royal BAM Group

The construction of the Fehmarnbelt tunnel took another major step forward on Thursday, September 21. Early in the morning, the construction consortium Femern Link Contractors (FLC) switched on the pumps that will fill water into the three large basins at the tunnel factory in Rødbyhavn.

The Fehmarnbelt project is the largest construction site in Northern Europe, and the filling of the basins is part of a complicated process that must be completed before the tunnel elements can be shipped out next year.

Our contractors have been working on the basins for more than two years, so naturally we have all been anxious to start filling them. It is always exciting when you do something for the first time, and the basins play a key role in the project. Their size alone makes this a spectacular day on the construction site,” commented Anders Wede, Construction Manager at Femern A/S.

The water filling is done gradually in a carefully controlled process so as not to damage the barriers between the basins, and it is therefore expected to take up to a week before they are completely full. The pools are also of a size not seen anywhere else in Northern Europe.

Each basin has a depth of almost 11 meters and together they hold around 1.6 million cubic meters of water. That is the same amount of water as 640 Olympic swimming pools.

The basins are the link between the factory and the work harbour, from where the elements are shipped out. Large gates ensure that the dry dock and basins can be filled with water and emptied as needed, allowing the elements to float from the factory to the work harbour and further out into the Fehmarnbelt.

With the filled basins, the tunnel factory is close to complete. The two large gates that will control the water level in the basins are well underway, and inside the factory we have started casting the tunnel elements. The next big milestone will come next year, when we will ship out the first finished element,” said Wede.

The first tunnel element is expected to be immersed in 2024.