DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Dredging›$40M contract awarded for Chesapeake Bay restoration project
Dredging

October 10, 2024 · about 1 year ago

$40M contract awarded for Chesapeake Bay restoration project

Seacoast Marine Construction of Long Island, New York, recently won a $39.9 million USACE contract for restoration work at Barren Island, part of the Mid-Chesapeake Bay Island Ecosystem Restoration project in Dorchester County, Maryland. The contract award ushers in the second phase of Mid-Bay resto

2 minutes read
  • LinkedIn
  • X
  • Email
$40M contract awarded for Chesapeake Bay restoration project
Photo courtesy of USACE

Share this article

Seacoast Marine Construction of Long Island, New York, recently won a $39.9 million USACE contract for restoration work at Barren Island, part of the Mid-Chesapeake Bay Island Ecosystem Restoration project in Dorchester County, Maryland.

The contract award ushers in the second phase of Mid-Bay restoration work on Barren Island including construction of two bird islands adjacent to the existing island and connected to the breakwater; construction of stone sill structures; design and installation of spillway structures; and excavation of material from the Honga & Tar Bay federal navigation channels and placement within a contained area adjacent to Barren Island.

Approximately 335,000 cubic yards of material consisting of mud, sand, silt, shell and combinations thereof will be removed via hydraulic dredge from the Honga River channel to its authorized depth of seven feet and a width ranging from 60-140 feet.

The Mid-Bay project, in partnership with MDOT MPA, includes restoration of 2,072 acres of lost remote island habitat on James Island and 72 acres of remote island habitat on Barren Island, using material dredged from the Port of Baltimore approach channels and shallow draft federal navigation channels, respectively.

Barren Island is anticipated to begin acceptance of Honga River dredged material in late 2025 or early 2026, with James Island accepting dredged material around 2030, after sill and dike construction efforts to hold the material are completed at each location. The Honga River channel was last dredged by USACE in 2009.

USACE received more than $80 million in funding from the Bipartisan Infrastructure Law in 2022 to complete the design and preconstruction activities for the Barren Island component of this project, to include the first construction contract award. The Mid-Bay project is anticipated to be completed in 2067 – providing more than 30 years of capacity to place nearly 95 million cubic yards of dredged material.

Poplar Island, the ongoing ecosystem restoration project by USACE and MDOT MPA, wrapped up construction of an expansion effort in January 2021 that provides substantial ecosystem benefits and additional dredge material capacity for the approach channels to the Port of Baltimore until 2032.

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

DredgingEnvironment

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1USACE starts feasibility study for Cooper River deepening
  2. 2BREAKING NEWS: Dutch Dredging takes delivery of new TSHD Magdalena
  3. 3Stockton closes boat launch due to dredging work
  4. 4E-touch Dredgers: Work on new TSHD progresses steadily

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free