DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Beach Nourishment›Kure Beach renourishment to be postponed, Mayor Allen Oliver says
Beach Nourishment

January 15, 2025 · about 1 year ago

Kure Beach renourishment to be postponed, Mayor Allen Oliver says

The mayor of Kure Beach, Allen Oliver, has sent out a letter about the recent development of the beach renourishment project, saying that the results of the opening bid for the Kure Beach solicitation were ‘less than favorable.’ According to Oliver, only one package was submitted (Weeks Marine) with

1 minutes read
  • LinkedIn
  • X
  • Email
Kure Beach renourishment to be postponed, Mayor Allen Oliver says
photo courtesy of Kim Singleton fb

The mayor of Kure Beach, Allen Oliver, has sent out a letter about the recent development of the beach renourishment project, saying that the results of the opening bid for the Kure Beach solicitation were ‘less than favorable.’

According to Oliver, only one package was submitted (Weeks Marine) with a bid price of $37.5 million compared to the town’s independent government estimate of $19.6 million.

“I anticipate that we will cancel this solicitation, and move to reissue a solicitation targeting a contract award in the summer of 2025. This would push the scheduled renourishment cycle out another year. We will again be targeting the environmental window of 16 November 2025 to 30 April 2026,” Mayor Oliver wrote in the letter.

“We should get better pricing and more bidders participating. The reality is most contractors had projects awarded in other areas and they didn’t bid on our project because of the lateness in sending out the solicitation for bids. We have heard the USACE will advertise for bids late April to early May.”

“No specific dates have been set,” Oliver concluded.

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Beach Nourishment

Daily Dredging and Port Construction News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Premier Marinas submits Brighton dredging application
  2. 2Dredging underway at Everett Harbor and Snohomish River
  3. 3PD Ports opens new Marine facility
  4. 4PHOTO OF THE DAY: Swiss Army Knife of Great Lakes in Ashtabula

Daily Dredging and Port Construction News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free