DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Beach Nourishment›Melbourne Beach restoration plan unveiled
Beach Nourishment

December 15, 2025 · about 8 months ago

Melbourne Beach restoration plan unveiled

Brevard County has introduced a plan to restore the South Reach section of shoreline near Melbourne Beach between December 2025 and April 2026 as part of a scheduled beach restoration project. The 3.8-mile South Reach begins at Flug Avenue in Indialantic and extends south to Spessard Holland Park No

1 minutes read
  • LinkedIn
  • X
  • Email
Melbourne Beach restoration plan unveiled
photo courtesy of brevardfl.gov

Brevard County has introduced a plan to restore the South Reach section of shoreline near Melbourne Beach between December 2025 and April 2026 as part of a scheduled beach restoration project.

The 3.8-mile South Reach begins at Flug Avenue in Indialantic and extends south to Spessard Holland Park North. The U.S. Army Corps of Engineers is managing the project, and its contractor Dutra Group is staging equipment between Spessard Holland Park North and Spessard Holland Park South.

“ The two parks will generally remain open during the work, but the beach area between them may close at times. Spessard Holland South will always remain open ,” according to the county’s website .

“Crews expect to begin active sand placement near Spessard Holland Park in early January and proceed northward.”

The Town of Melbourne Beach said that the contractor plans to start assembling the pipe on the beach in mid-late December and start pumping sand in mid-January.

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Beach Nourishment

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1USACE starts feasibility study for Cooper River deepening
  2. 2BREAKING NEWS: Dutch Dredging takes delivery of new TSHD Magdalena
  3. 3Stockton closes boat launch due to dredging work
  4. 4E-touch Dredgers: Work on new TSHD progresses steadily

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free