DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Dredging›Fountain Lake dredging underway
Dredging

May 20, 2026 · about 3 months ago

Fountain Lake dredging underway

The Fountain Lake dredging program is underway, the Shell Rock River Watershed District said. The District’s Board of Managers has approved a $7.7 million contract with J.F. Brennan Co. for the third and final phase of sediment removal on Fountain Lake. In recent weeks, crews were on-site installing

1 minutes read
  • LinkedIn
  • X
  • Email
Fountain Lake dredging underway
photo courtesy of Shell Rock River Watershed District

The Fountain Lake dredging program is underway, the Shell Rock River Watershed District said.

The District’s Board of Managers has approved a $7.7 million contract with J.F. Brennan Co. for the third and final phase of sediment removal on Fountain Lake.

In recent weeks, crews were on-site installing pipe for the dredging project. The pipe system moves a mixture of water and lake sediment from the dredging equipment to a disposal site north of Interstate 90. Pumps help keep the material flowing through the pipeline, which is placed both in the water and on land.

According to the District, this process removes phosphorus-rich sediment from the lake bottom, helping improve water quality and reduce internal phosphorus loading.

The material removed from the lake will be pumped to a dewatering site, where water is separated and eventually returned to Fountain Lake. The disposal area includes three engineered cells spanning more than 100 acres and can hold over millions of cubic yards of sediment.

Sediment removal will start in Bancroft Bay and continue throughout the 2026 construction season. Work in East Main Bay is scheduled for the 2027 season.

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Dredging

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1USACE starts feasibility study for Cooper River deepening
  2. 2BREAKING NEWS: Dutch Dredging takes delivery of new TSHD Magdalena
  3. 3Stockton closes boat launch due to dredging work
  4. 4E-touch Dredgers: Work on new TSHD progresses steadily

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free