DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Beach Nourishment›BREAKING NEWS: Jan De Nul’s work in Itapoá enters final stage
Beach Nourishment

June 22, 2026 · about 2 months ago

BREAKING NEWS: Jan De Nul’s work in Itapoá enters final stage

The Port of São Francisco said that the final stage of one of the largest coastal engineering projects ever carried out in Brazil – the Itapoá work – is nearing its completion. The Figueira do Pontal Beach will be the last stretch contemplated by the widening works of the Itapoá shore. The start of

2 minutes read
  • LinkedIn
  • X
  • Email
BREAKING NEWS: Jan De Nul’s work in Itapoá enters final stage
photo courtesy of Porto de São Francisco do Sul

The Port of São Francisco said that the final stage of one of the largest coastal engineering projects ever carried out in Brazil – the Itapoá work – is nearing its completion.

The Figueira do Pontal Beach will be the last stretch contemplated by the widening works of the Itapoá shore. The start of feeding the 800 meters of this sand strip is scheduled for next Friday, June 26, marking the final phase of the coastal reconstruction carried out by Jan De Nul.

So far, the coastal strengthening works have achieved 93% execution. Of the 8.8 kilometers predicted in the project, 7.3 kilometers have already received new sand.

“In Itapoá, we combine two major challenges: improving access to the Baía da Babitonga and strengthening a vulnerable coastline. During the first phase, carried out in the autumn of 2025, our trailing suction hopper dredger Galileo Galilei deepened the access channel to the port. We reused the dredged sand to widen a degraded stretch of coastline, ” Jan De Nul said. To improve maritime accessibility, the company increased the depth of the access channel from –14 to –16 meters. In total, Jan De Nul removed 11.9 million cubic meters of sand. This deepening allows larger vessels to reach the port safely and increases the region’s logistical capacity.

“ We link the deepening of the access channel to targeted coastal protection, demonstrating our commitment to sustainable marine engineering solutions. By guiding natural sediment flows, we protect infrastructure and communities while restoring ecological balance along the coast ,” said Jan De Nul .

This project is the result of a public‑private partnership between the São Francisco do Sul Port Authority and the Itapoá Terminal.

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Beach NourishmentBusiness developmentCoastal ProtectionCoastal RestorationDredgingEquipmentInfrastructureMaintenance DredgingPort ExpansionSand PumpingTechnology

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1USACE begins Lower Charleston Harbor maintenance dredging
  2. 2London Gateway Berth 5 expansion: Dredging campaign underway
  3. 3University of Southern Denmark: New project to restore polluted lakes
  4. 4Van Hollen, Alsobrooks secure $20M for Ocean City beach replenishment

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free