McLaughlin & Harvey said that the development operations are moving forward at the Port of Nigg project.
The existing rock armor has now been removed from the revetment, with rock bund construction progressing and infilling operations underway.
According to the company's latest update, these works - undertaken for Maraen - are preparing the site for the next phase of construction, with piling due to commence in October.
Representing an investment of more than £30 million, the Eastern Inner Dock Quay (EIDQ) will deliver a new 16,000m² heavy-duty quay, expanding the port's Ro-Ro capability and creating a dedicated facility for cable export operations.