Dredging begins on Charlotte Amalie Harbor

EG

Eldin Ganic

Dredging Today

2 minutes read
photo courtesy of VIPA
photo courtesy of VIPA

Virgin Islands Port Authority (VIPA) Executive Director Ava Penn said that mobilization is underway for the long-awaited Charlotte Amalie Harbor Dredging Project, with dredging activity anticipated to begin by Friday, November 27, 2026.

The project involves dredging the harbor's entrance channel, turning basin, and West Indian Company Limited (WICO) berthing pocket in Havensight. The improvements will increase controlling depths in key areas of the harbor and enhance vessel maneuverability.

According to VIPA, this multimillion-dollar maritime infrastructure investment will improve navigational access to the Charlotte Amalie Harbor, accommodate the evolving needs of the cruise industry, and strengthen the U.S. Virgin Islands' position as a premier Caribbean cruise destination.

Preparations for the dredging project are underway on both St. Croix and St. Thomas. 

On St. Croix, barges supporting the project arrived in the Territory on Saturday, November 14, and Sunday, November 15, 2026. Preparation of the temporary stockpile site, including clearing and grubbing activities, has begun.

Also, silt fences were installed last weekend, and stabilized entrances to the site were constructed this week. Preparation of the designated quarry site will follow completion of the temporary stockpile site.

The Charlotte Amalie Harbor Dredging Project will be conducted in two phases:

  • Phase 1 — November 2026 through March 2027: This phase will consist of dredging the non-beach quality material from the entrance channel, turning basin, and WICO berth pocket. The material will be transported via vessel from the Charlotte Amalie Harbor to the south shore of St. Croix, where it will be temporarily placed for dewatering at the Gordon A. Finch Molasses Pier in Krause Lagoon. It will then be transported via truck for final placement at a quarry site on the north side of the Henry E. Rohlsen Airport,
  • Phase 2 — March 2027 through October 2027: This phase will consist of dredging the beach-quality material from the entrance channel. The material will be transported via vessel to Crown Bay Cargo Port for unloading. It will then be transported by truck to the former Addelita Cancryn Junior High School property.

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Daily Dredging and Port Construction News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.