  • 24 April 2020
    Business & Finance

    J.E. McAmis said in its latest announcement that their crews in Longview, WA yard are putting a new timber deck on the ABS Deck Barge – Ellis Island. The Ellis Island (250′ x 76′) will be put into service at the Mouth of the Columbia River to provide critical infrastructure at the South Jetty for […]

  • 14 April 2020
    Business & Finance, Project & Tenders

    Because of the bad weather, construction works on the Phase II of the Post Florence Renourishment Project were briefly paused last Sunday, according to the Carteret County Shore Protection Office. As reported, the hopper dredge Ellis Island went into safe harbor to avoid the rough seas and took this opportunity to refuel. The work is […]

  • 23 March 2020
    Business & Finance, Project & Tenders, Vessels

    As scheduled one the largest hopper dredges in the United States, the Ellis Island has arrived in Carteret County and is now pumping sand on to the Pine Knoll Shores. According to the County Shore Protection Office, the Ellis Island arrived on March 19, underwent environmental testing (mostly related to sea turtle protection), and started […]

  • 3 March 2020
    Business & Finance

    Great Lakes Dredge & Dock Corporation (GLDD) last week hosted visitors from the U.S. Army Corps of Engineers, South Carolina Department of Natural Resources (SCDNR), SC Aquarium and other Charleston Deepening environmental stakeholders aboard their trailing suction hopper dredger (TSHD) Ellis Island. “While giving our visitors a firsthand look at our operations and proactive measures […]

  • 29 May 2019
    Business & Finance

    The Town of Nags Head, North Carolina, has just released the latest update on their coastal construction project, saying that the dredger Liberty Island is beginning beach nourishment work near the Curlew Street public beach access at about Mile Post 11.5. The other Great Lakes Dredge and Dock’s dredger Ellis Island remains in Norfolk due […]

  • 20 November 2017
    Business & Finance, Project & Tenders, Vessels

    Great Lakes Dredge & Dock Corporation (GLDD) has taken delivery of the new build ATB hopper dredge Ellis Island and tug Douglas B. Mackie after successful completion of United States Coast Guard and American Bureau of Shipping regulatory sea trials. David Simonelli, President, Dredging Division commented: “We are excited to take delivery of this advanced vessel […]

  • 18 May 2020
    Business & Finance

    The U.S. Army Corps of Engineers, New England District is proposing to perform maintenance dredging of the Wood Island and Pool at Biddeford Federal Navigation Project (FNP) in Biddeford, Maine. The proposed work involves maintenance dredging of portions of the 10-foot-deep Mean Lower Low Water (MLLW) Federal navigation channel and 6-foot-deep basin at Biddeford Pool, […]

  • 9 June 2011

    Excavation of a yacht basin at Big Bell Island in the Exuma Cays Land and Sea Park is underway as owner the Aga Khan forges ahead with… By MEGAN REYNOLDS (tribune242) [mappress] Source: tribune242, June 9, 2011  

  • 27 October 2010

    As approval for a controversial development in Bell Island was revealed yesterday, The Tribune was frustrated in its efforts to obtain the… By Megan Reynolds (tribune242) [mappress] Source: tribune242, October 27, 2010;

  • 9 June 2020
    Business development, Equipment, Infrastructure, Technology, Vessels

    Great Lakes Dredge & Dock Corporation (GLDD) announced today the execution of a definitive contract for the construction of a 6,500-cubic-yard-capacity trailing suction hopper dredge. With expected delivery in the 1st quarter of 2023, the vessel will complement the company’s existing six-dredge hopper fleet, including the ATB Tug Douglas B. Mackie and 15,000-cubic-yard-capacity barge Ellis […]

  • 30 April 2020
    Business & Finance, Project & Tenders, Vessels

    Great Lakes Dredge & Dock has successfully completed Phase II of the Post Florence Renourishment Project. According to the Carteret County Shore Protection Office, GLDD’s hopper dredge Ellis Island delivered the last load of sand to West Emerald Isle (“reach 2”) at approximately 1:30 pm, on April 29th signifying the conclusion of the beach nourishment […]

  • 21 April 2020
    Business & Finance

    J.E. McAmis, a heavy-civil, marine and environmental contractor, has just released a couple of updates on two new additions to the JEM Marine barge fleet. The San Clemente Island (250′ x 72′ x 15′) just came off of Vigor’s drydock in Portland and is headed back to WCT in Astoria for final outfitting and the […]

  • 17 April 2020
    Business & Finance

    After this early week’s storm and coincident refueling of the hopper dredger Ellis Island, Carteret County is back to work pumping sand from a submerged pipeline (Line 7) that emerges near the Sea Dunes Subdivision.  “Nourishment is currently progressing east from this point, and after this morning’s pump-out of a load of sand, we are […]

  • 7 April 2020
    Business & Finance, Project & Tenders, Vessels

    The Carteret County Shore Protection Office announced yesterday that they are right on track with the Phase II of the Post Florence Renourishment Project. Great Lakes Dredge & Dock and their hopper dredge Ellis Island have been working uninterrupted and completed the Pine Knoll Shores reach (“Reach 9”) on April 3rd, reported the Shore Protection […]

  • 3 April 2020
    Business & Finance, Project & Tenders, Vessels

    Trailing suction hopper dredge Ellis Island has been working non-stop this week on the beach nourishment project in Carteret County, NC. According to the county officials, Great Lakes Dredge & Dock has just completed the Pine Knoll Shores portion of the project. Now, the contractor will fully transition to Salter Path. Sand for this portion […]

  • 31 March 2020
    Business & Finance, Project & Tenders

    Despite a persistent southwest wind generating choppy seas past weekend, Great Lakes Dredge & Dock is making great progress in Carteret County. According to the county’s Shore Protection Office, GLDD dredge the Ellis Island has completed pumping sand in the eastward direction from the submerged pipeline landing in Beacon’s Reach. “We’re now pumping sand westward […]

  • 29 March 2020
    Business & Finance

    Dredging Today brings you an overview of the most popular stories from the past week (March 23-29, 2020).   Hopper Dredge Ellis Island Arrives in Carteret County As scheduled one the largest hopper dredges in the United States, the Ellis Island has arrived in Carteret County and is now pumping sand on to the Pine […]

  • 9 March 2020
    Business & Finance, Project & Tenders, Vessels

    The Carteret County Shore Protection Office has presented the latest update regarding the county’s Post Florence Renourishment Project. According to the update, the dredge Liberty Island has been the only dredge on site since the project started on February 8th. “The dredge has been tremendously productive delivering approximately 522,000 cubic yards in reach 10 (basically Atlantic […]

  • 12 February 2020
    Business & Finance

    In the newly released fiscal year 2021 President’s Budget, the White House included over $100 million for the Port of Corpus Christi’s Ship Channel Improvement Project (CIP) under the U.S. Army Corps of Engineers (USACE) Civil Works Division for Coastal Navigation Construction.  This is the third consecutive year that the Port of Corpus Christi has been included in the President’s proposed budget. “The Corpus […]

  • 11 February 2020
    Business & Finance, Project & Tenders

    Works on the Phase II of the Carteret County Post Florence Renourishment Project are in full swing now, informs the county’s Shore Protection Office. “As expected, we’re experiencing some strong productivity a little over two days into the project as the sand is being pumped eastward from the first subline landing,” the county said. The […]

  • 24 January 2020
    Business & Finance

    Phase II of the Carteret County Post Florence Renourishment Project is scheduled to begin in the first week of February, the Shore Protection Office reports. According to the officials, Great Lakes Dredge & Dock (GLDD) plans to mobilize land- and water-based pipe, heavy equipment, personnel, etc. this week and dredging/pumping is scheduled to begin in […]

  • 4 November 2019
    Business & Finance

    Maj. Gen. Scott A. Spellmon, Deputy Commanding General for Civil Works and Emergency Operations, U.S. Army Corps of Engineers, Headquarters, visited the Galveston District last week as part of a two-day Corpus Christi Ship Channel Improvement Project update. On the second day of his visit, he was joined by Brig Gen. Paul Owen, commander, U.S. Army […]

  • 2 October 2019
    Business & Finance

    Great Lakes Dredge & Dock Corporation (GLDD) announced today the receipt of several major dredging awards totaling $178 million. The awarded work includes: Mississippi Coastal Improvements Program (MSCIP), Comprehensive Barrier Island Restoration Plan (Coastal Restoration, Mississippi, $56.7 million); Great Egg/Peck Beach New Jersey (Coastal Protection, New Jersey, $32.5 million) Post-Florence Renourishment Project (Coastal Protection, North […]

  • 30 August 2019
    Business & Finance, Project & Tenders

    Great Lakes Dredge & Dock Corporation (GLDD) has successfully completed the Nags Head beach nourishment project. The beach nourishment sand pumping operations were completed early on Sunday morning, August 18, 2019 in the 8200 block of South Old Oregon Inlet Road near Mile Post 17, reported the town. During the 2019 beach nourishment campaign, GLDD’s […]

  • 1 July 2019
    Business & Finance, Project & Tenders

    Hopper dredger Liberty Island has returned to Nags Head and is hard at work nourishing the beach in the vicinity of the submerged pipeline near the Epstein public beach. According to the town officials, now the dredger is back the construction will progress north over the next 10 days or so to tie into the […]

  • 19 June 2019
    Business & Finance, Project & Tenders, Vessels

    The Town of Nags Head, North Carolina, has released new info about their beach nourishment project. Last evening, Tuesday, June 18, 2019, the town announced that the sand pumping operations have ceased temporarily as the Dredge Liberty Island needs to sail to Norfolk for re-fueling. At this time, the town officials anticipate that the construction […]

  • 12 June 2019
    Business & Finance, Project & Tenders

    Due to a leak in the submerged pipe through which sand is pumped from offshore onto the beach, nourishment operations south of Outer Banks Pier, near Mile Posts 18.5-19, have stopped, reports the Town of Nags Head, NC. As a result, the Dredge Ellis Island, which was working off that submerged line, is now operating […]

  • 6 May 2019
    Business & Finance, Project & Tenders, Vessels

    Nags Head’s beach nourishment is now underway with the Dredge Ellis Island pumping sand onto the beach just south of Limulus Street, reports the Town of Nags Head, NC. According to the report, the Town is conducting a 90-120 day-long beach nourishment maintenance project, which started May 1, 2019. The current schedule calls for the […]

  • 26 April 2019
    Business & Finance, Project & Tenders, Vessels

    Great Lakes Dredge & Dock’s hopper dredge Liberty Island yesterday delivered the last load of sand to eastern Emerald Isle, marking the completion of dredging/pumping activities for Phase I of the post-Florence Renourishment Project. Following the completion of the works, GLDD’ dredge Liberty Island departed the site yesterday afternoon for her next project. The project […]