Search results for: Havant

39 results

A list of search results

  • 10 May 2013

    Havant Borough Council Capital Projects Team has awarded the Havant coastal defence project to the Raymond Brown Construction Ltd. This development program consists of the following activities: – Construction of a 650m rock revetment (27,700m3, 3-6 tonnes of rock armour); – Construction of 3 no. 90m rock groynes (7,000m3, 3-6 tonnes rock armour); – Import […]

  • 5 January 2018
    Business & Finance

    As a part of the ongoing beach management plan for South Hayling Island, Havant Borough Council will be undertaking beach renourishment works during January and February 2018 to rebuild the beach after the recent stormy weather. The Eastern Solent Coastal Partnership (ESCP) anticipates that these works will begin during the week commencing the 8th January, and […]

  • 24 August 2016
    Business & Finance

    Coastal works are being carried out on some failed sections of the revetment near the Broadmarsh Coastal Park in Havant. Storms over the winter of 2015/16, and further storms in the spring of 2016 caused damage to the concrete, and repairs are now being undertaken to ensure that the defense remains operational. The revetment was […]

  • 22 April 2016
    Business & Finance, Project & Tenders

    Havant MP Alan Mak recently joined representatives from the government on a walk of the Hayling Billy Trail, inspecting flood defense work at Eastoke. The local MP joined Natural England’s Area Manager, Fran Davies, on what may form part of the Portsmouth to South Hayling stretch of the new England Coast Path. The England Coast Path, the biggest access […]

  • 30 May 2018
    Business & Finance

    Funding to develop designs for a new coastal defense scheme which could protect homes from flooding and erosion in Langstone has been secured, the Havant Borough Council (HBC) informs.  The Eastern Solent Coastal Partnership (ESCP), on behalf of HBC, has secured £376,000 made up from a Defra Grant in Aid and the HBC Community Infrastructure […]

  • 5 November 2015
    Business & Finance, Project & Tenders, Vessels

    The Eastern Solent Coastal Partnership for Havant Borough Council successfully carried out a beach nourishment campaign along Hayling Island from the 31st October 2015 to 1st November 2015. The campaign involved dredging approximately 6,200m³ of shingle from the approach channel to Chichester Harbor, where the shingle material has naturally built up. It was then pumped […]

  • 1 April 2016
    Business & Finance, Project & Tenders

    Havant Borough Council has begun with the beach management operations along the Hayling Island seafront in accordance with the Beach Management Plan for this area. The works started on 29th March 2016 and will last for approximately 3-4 weeks. Beach management comprises both beach recycling and beach nourishment. The council has appointed Boskalis Westminster Limited to undertake the beach […]

  • 7 January 2015
    Business & Finance, Equipment, Technology

    Approximately 10,000m3 of dredged shingle has been deposited on the beaches of Eastoke, Hayling Island. The 73 m-long trailing suction hopper dredger “Sospan Dau” used a technique known as ‘rainbowing’ to discharges a mixture of sediment and water and create a mound of material high on the foreshore. This project took place during the last weekend […]

  • 25 February 2020
    Business & Finance

    After successfully securing funding from the Environment Agency, Havant Borough Council is carrying out the next beach recycling campaign along the Eastoke frontage. The aim of this campaign is to reinstate the beach to the 1:200 year design standard of protection, reducing the risk of coastal flooding and erosion to properties and infrastructure. According to […]

  • 20 March 2018
    Business & Finance

    As part of the Eastern Solent Coastal Partnership (ESCP) ongoing Beach Management Plan for South Hayling Island, Havant Borough Council is undertaking beach renourishment works during March 2018 to return the beach at Eastoke to full design profile. These works started on 12th March, and will last for a period of 2-3 weeks, reports ESCP. “The […]

  • 27 March 2019
    Business & Finance

    The Eastern Solent Coastal Partnership is working with consultants AECOM, on behalf of Havant Borough Council, to carry out an economic footprint study for Hayling Island. As part of this, a short questionnaire has been developed to help understand the direct and indirect impacts of coastal flooding and erosion on Hayling Island and the wider […]

  • 15 June 2017
    Business & Finance

    Eastern Solent Coastal Partnership (ESCP) sea defense inspections following the first storm of 2016 (Storm Angus) identified damage to the fragile coastal revetments at Broadmarsh. In light of the regular failures of this defenses, ESCP made proposal to replace the section of damaged concrete revetment with rock revetment (used already by the ESCP at North […]

  • 8 January 2018
    Business & Finance

    Since the previous timber maintenance works at the Eastoke Frontage, further damage has been identified to the structure, announced the Eastern Solent Coastal Partnership (ESCP). ESCP said that they will begin timber maintenance on the groynes and the sloping timber revetment in front of the Coastguard Station during the week commencing 15th January 2018. The […]

  • 30 March 2020
    Business & Finance

    This spring’s beach management activities at Hayling Island which consist of recycling beach material from Gunner Point and the Coast Guard Revetment to the Eastoke frontage are now complete, Eastern Solent Coastal Partnership (ESCP) reports.  Contractor Les Searle Group moved over 33,000m³ of material for Havant Borough Council, making impressive progress in just three weeks. […]

  • 29 October 2012

    Expressions of interest are invited from suitably qualified and experienced providers to tender for Eastoke Point Coastal Defence Scheme. The scope of the contract will comprise of but may not be limited to: – Construction of a 650m rock revetment (27,700m3, 3-6 tonne rock armour); – Construction of three 90m rock groynes (7,000m3, 3-6 tonne […]

  • 19 February 2020
    Business & Finance

    Following a series of extreme storms which have battered the coast, Havant Borough Council has fenced off an area at West Beach, Hayling Island, and will be removing one of the damaged coastal defenses.     In the interests of safety, engineers from the Eastern Solent Coastal Partnership (ESCP) will carry out further inspections and will […]

  • 18 October 2017
    Business & Finance

    Mackley is currently carrying out a program of beach replenishment works on Hayling Island in Hampshire, as part of a wider scheme to protect the area from flooding. The South Hayling Beach Management Plan provides flood risk management to protect approximately 1,500 homes in the south of Hayling Island. Mackley has been contracted by the East […]

  • 8 June 2015
    Business & Finance

    A program of beach management was carried out recently along the Eastoke frontage of Hayling Island. The shingle beach along Eastoke is the primary line of defense against erosion and flooding, however coastal processes are constantly eroding the shingle bank. Without regular intervention, the densely populated area of Eastoke would quickly become vulnerable to flooding […]

  • 25 October 2019
    Business & Finance, Project & Tenders, Vessels

    The maintenance dredging operations in Chichester Harbor Approach Channel and nourishment of the Hayling Island are progressing nicely, according to the Eastern Solent Coastal Partnership – ESCP. After securing funding from the Environment Agency, Havant Borough Council started this week with the beach nourishment of the Eastoke frontage. Material for this operation is being dredged […]

  • 7 November 2016
    Business & Finance, Project & Tenders, Vessels

    Havant Borough Council recently completed the beach management operations along the Hayling Island seafront in accordance with the Beach Management Plan for the area. The contractor, Boskalis Westminster Limited, used dredger – the Sospan Dau – to carry out the works. Around 25,000 cubic meters of shingle material was dredged from Chichester Harbor, transported a […]

  • 28 September 2016
    Business & Finance, Project & Tenders

    Havant Borough Council has started with the combined maintenance dredge of the Chichester Harbor Approach Channel and nourishment to the Eastoke Frontage, Hayling Island. The maintenance dredge of the approach channel is underway, with a maximum volume of 25,000m³ of material to be pumped onto the beach along the Eastoke frontage. The exact location will vary […]

  • 26 July 2017
    Business & Finance

    ABPmer has teamed up with Capita AECOM to help the Environment Agency undertake a new managed realignment project in Southmoor, Langstone Harbor.   This project will involve building a new seawall at the back of the site and placing a breach in the old seawall to allow the sea to flow gently into the site […]

  • 13 November 2016
    Business & Finance, Project & Tenders

    Dredging Today brings you an overview of the most popular stories from the past week (November 7 – November 13, 2016).   Boskalis Completes Hayling Island Beach Renourishment Havant Borough Council recently completed the beach management operations along the Hayling Island seafront in accordance with the Beach Management Plan for the area.   TSHD Kadosh […]

  • 13 August 2018
    Business & Finance

    Havant Borough Council (HBC) and the Eastern Solent Coastal Partnership (ESCP) are continuing their work to develop outline designs for sea defenses at Langstone. The scheme is aimed to reduce coastal flood and erosion risk to 86 properties over the next 100 years, as well as critical infrastructure including the A3023, the only road access […]

  • 2 November 2015
    Business & Finance, Project & Tenders

    Boskalis Westminster dredger Sospan Dau has just completed maintenance dredging of the approach channel to Chichester Harbor and beach nourishment at Hayling Island. The approach channel to the harbor was dredged, targeting areas where the shingle material has naturally built up which could otherwise cause a navigation risk to local mariners. Approximately 7,000m³ of material was pumped onto the beach in […]

  • 2 January 2017
    Business & Finance, Equipment, Technology, Vessels

    Dredging Today brings you an overview of the most popular news articles from the past year.   World’s First LNG-Powered TSHD Minerva Hits the Water The launch ceremony of DEME’s 3,500m³ LNG-powered trailing suction hopper dredger (TSHD) Minerva took place on December 3 at Royal IHC’s shipyard in Kinderdijk, the Netherlands.   Van der Kamp […]