Search results for: Muddy River

38 results

A list of search results

  • 6 May 2020
    Business & Finance

    Phase 2 of the Muddy River Flood Risk Management construction project in Boston and Brookline, Massachusetts, will be completed under the terms of a $36.5 million contract issued by the U.S. Army Corps of Engineers, New England District. The non-Federal sponsors for the project are the Commonwealth of Massachusetts, the City of Boston, and the […]

  • 18 April 2017
    Business & Finance

    Federal, state and local partners will mark the completion of Phase 1 of the $30.9 million Muddy River Flood Risk Management project in a ribbon cutting ceremony of the Justine Mee Liff Park on April 21, 2017 in Boston, the U.S. Army Corps of Engineers just announced. The Muddy River project was in response to […]

  • 4 April 2017
    Business & Finance

    The Muddy River Flood Risk Management and Environmental Restoration Project in Boston, Massachusetts, recently received the Associated General Contractors (AGC) of America’s Alliant Build America Award, the U.S. Army Corps of Engineers, New England District, said. The 3.5 mile long Muddy River is a small waterway located in the Boston metropolitan area. Most of the […]

  • 5 July 2016
    Business & Finance, Project & Tenders

    Construction activities are coming to a close on Phase 1 of the $30.9 million Muddy River Flood Risk Management and Environmental Restoration project in Boston, Massachusetts. On Monday, June 27th, the final temporary river diversion steel sheeting was removed from upstream of the new Riverway Culvert and the Muddy River was flowing freely and completely […]

  • 24 December 2015
    Business & Finance

    Construction activities continue on Phase 1 of the $30.9 million Muddy River Flood Risk Management and Environmental Restoration project in Boston, Massachusetts. On Saturday, December 19, the temporary river diversion bypass pumps were turned off at about 10:30 a.m. and the river was flowing by 11:00 a.m. from Upper Fens Pond to Avenue Louis Pasteur […]

  • 19 March 2015
    Business & Finance

    Construction activities continue on Phase 1 of the $30.9 million Muddy River Flood Risk Management and Environmental Restoration project in Boston, Massachusetts. On Saturday, March 21, Jug Handle roadway will be closed to vehicular and pedestrian traffic in order to install the piping beneath the roadway for the river diversion work. Vehicular traffic will be […]

  • 9 September 2014
    Business & Finance, Equipment, Technology

    Construction activities continue on Phase 1 of the $30.9 million Muddy River Flood Risk Management and Environmental Restoration project in Boston, Massachusetts. On Saturday, September 20, another traffic shift to change both vehicular and pedestrian traffic will occur to begin construction of the arch culvert underneath Riverway. This traffic shift will maintain the current traffic […]

  • 23 September 2013

    At the request of the City of Boston Transportation Department, the Corps of Engineers is delaying the traffic pattern change to Brookline Avenue until 7 a.m. on Saturday, Sept. 28, 2013. Construction activities continue on Phase 1 of the $30.9 million Muddy River Flood Risk Management and Environmental Restoration project in Boston, Mass., and starting […]

  • 11 September 2013
    Business & Finance

    Construction activities continue on Phase 1 of the $30.9 million Muddy River Flood Risk Management and Environmental Restoration project in Boston, Mass., and starting on Sept. 16 will involve a change in both vehicular and pedestrian traffic. Brookline Avenue between the Riverway Connector and Park Dive will become one-way only headed inbound. Traffic coming down […]

  • 17 January 2013
    Business & Finance

    Construction activities on Phase 1 of the $30.9 million Muddy River Flood Risk Management and Environmental Restoration project in Boston, Mass., will start on or about Jan. 28, 2013 with tree removal and then followed by fencing and barrier installation. The construction project is located in the footprint generally between the Riverway and downstream to […]

  • 15 October 2012

    Officials from the Commonwealth of Massachusetts, the city of Boston, the town of Brookline and the U.S. Army Corps of Engineers broke ground on Oct. 10 on Phase 1 of the $30.9 million Muddy River Flood Risk Management and Environmental Restoration project in Boston, Mass. “The overall project objectives are to reduce flood risk and […]

  • 15 August 2012

    Phase 1 of the Muddy River Flood Risk Management and Environmental Restoration project in Boston and Brookline, Mass., will be constructed under the terms of a $30,961,340.00 contract issued by the U.S. Army Corps of Engineers, New England District. Work will be accomplished by Charter Environmental of Boston, Mass. Construction is scheduled to start on […]

  • 5 December 2011

    After many decades, first major restoration of Olmsted’s park system will be undertaken in April 2012. The Massachusetts Commonwealth, City of Boston and Town of Brookline are the sponsors of the Muddy River project that is to be undertaken by the U.S. Army Corps of Engineers. The prospect of the joint federal, state, and local […]

  • 17 March 2011

    Preliminary work will begin by month’s end on a project to address flooding issues from the Muddy River, which runs from the Charles…   By Matt Rocheleau (boston) [mappress] Source: boston, March 17, 2011    

  • 28 September 2016
    Business & Finance

    PortsToronto is currently in the process of removing up to 40,000 cubic meters of debris and sediment from the mouth of the Don River. The main goals of this dredging scheme are preventing future flooding and stemming the flow of unwanted material into Toronto’s Harbor which can pose a risk to boater navigation and public […]

  • 23 September 2016
    Business & Finance

    PortsToronto is about to begin annual dredging project that will remove up to 40,000 cubic meters of debris and sediment from the mouth of the Don River. Each year, thousands of tons of sediment build up where the Don River empties into the Keating Channel which, if not removed, could cause the river to backup and […]

  • 4 December 2013

    The first phase of the River of Life project is nearly complete. Since October, when the project began, the Environment Agency and Earth Trust, working in partnership, have created seven new ponds, two reed beds and three new backwaters. Before Christmas arrives, there will be the excavation of a further two backwaters and a fen. […]

  • 18 October 2013
    Business & Finance

    The final stage of a £1m project to dredge 50,000 tonnes of sand, gravel and silt from the bed of the River Trent is taking place this week. “We started dredging the river in July to make it easier for leisure boats and cargo barges to cruise up and down. The project, the first major […]

  • 27 December 2012

    Residents give a boisterous welcome to Jakarta’s newly elected governor, Joko Widodo, when he shows up for a town meeting with the residents of a Jakarta slum where residents’ shacks overlook the muddy, garbage-strewn waters of the Ciliwung River. The governor’s administration plans to fix chronic flooding here by dredging the river and moving residents […]

  • 23 August 2011

    It’s a dirty job, but somebody’s got to do it. A tough, hardy little powerhouse, the Dredge Edward S. “Ned” Reed works up and down the Mississippi River on the east bank to provide access to the cruise terminals, where up to 5,000 people per cruise are likely to see him hard at work adjacent […]

  • 23 July 2018
    Business & Finance

    Maj. Gen. Jeffrey L. Milhorn assumed command of the U.S. Army Corps of Engineers’ North Atlantic Division from out-going commander Maj. Gen. William H. Graham during a ceremony at Fort Hamilton on July 20.  The U.S. Army’s 54th Chief of Engineers Lt. Gen. Todd Semonite, officiated and performed the symbolic transfer of the division colors […]

  • 20 June 2017
    Business & Finance

    The USACE’s New England District has once again collaborated with the Schools to Careers Partnership to sponsor a daylong event as part of the Program’s three-day Bioengineering Symposium. “This is the second year the District has done a full site tour – last year we toured Muddy River – but this is the fourth year […]

  • 5 June 2017
    Business & Finance

    The U.S. Army Corps of Engineers FY17 Civil Works Work Plan was finalized in late May 2017, allowing the New England District to plan for final project funding for the remainder of the fiscal year. In Connecticut, funding is available for operation and maintenance of the 8 Corps-managed flood risk management reservoirs, the Stamford Hurricane […]

  • 7 March 2014
    Business & Finance, Equipment, Technology

    With the release of the U.S. President Obama’s Budget for fiscal year 2015 for Corps of Engineers Civil Works on March 4, 2014, the Corps’ New England District looks forward to continued normal operations and funding. In Connecticut, the budget proposes continuing funding the operations and maintenance of the 8 Corps-managed flood risk management reservoirs […]

  • 5 March 2014
    Business & Finance, Equipment, Technology

    The U.S. President Obama’s Budget for fiscal year 2015 (FY15) included $4.561 billion in gross discretionary funding for the Civil Works program of the U.S. Army Corps of Engineers (USACE), which is offset in part by a proposal to cancel $28 million in unobligated carryover of funds previously appropriated. “The fiscal 2015 Civil Works budget […]

  • 16 May 2018
    Business & Finance, Equipment, Technology, Vessels

    Shipbuilding – Ship Repair Corporation from Gorodets, Nizhny Novgorod region, yesterday launched a non-self propelled cutter suction dredger (CSD) ‘Vladimir Panchenko’, Federal Marine and River Transport Agency Rosmorrechflot said in their latest release.  The 1,000 cbm/h dredgfer, designed by Rostov Central Design Bureau ‘Stapel’, is being built by the order of FSI Rechvodput as part of […]

  • 11 May 2017
    Business & Finance

    The Coastal Dynamics 2017 Conference will take place from June 12-16, 2017 in Helsingør, just north of Copenhagen, Denmark. The Coastal Dynamics conference series advances the community’s understanding of recent applied and basic research concerning coastal waves and currents, interactions between wind, water and sediments and morphology changes in different morphological environments (with and without structures) […]

  • 14 June 2016
    Business & Finance

    Magruder Construction, working as subcontractor to Phillips Hardy Inc., recently completed hydraulic dredging at Cora Island on the Missouri River. The Cora Island project is a component of the U.S. Army Corps of Engineers overall Missouri River Recovery Program. The work at the 1,358-acre island refuge is aimed at improving the habitat for several species […]

  • 3 November 2015
    Business & Finance, Equipment, Technology

    Wandsworth Council has introduced a plan to remove the half-tide weir on the River Wandle at Wandsworth with the main goal to allow the tidal river to return to its natural state to support biodiversity in central London. Funding for the project is being provided by Tideway, the company responsible for delivering the Thames Tideway […]