Search results for: North Dakota

5355 results

A list of search results

  • 18 August 2014
    Business & Finance, Equipment, Technology

    North Topsail Beach Board of Aldermen last week took action to begin the permitting process to install a sand bag revetment, also known as a geotube, along approximately 1,500 feet of shoreline on the north end of Topsail Island. This was in reaction to severe erosion that has been occurring in the area north of […]

  • 2 April 2013
    Business & Finance

    The U.S. Army Corps of Engineers has approved Project Implementation Reports that will result in renourishment of North and South Reach beaches in Brevard County, with the federal government footing virtually 100 percent of the estimated $29.3 million cost to restore parts of the county’s eroded shoreline. In late October 2012, Hurricane Sandy caused high […]

  • 9 September 2011

    Wasser- und Schifffahrtsamt Bremerhaven has announced tender for dredging works on the Weser waterway from km 55 to 91 (new) including survey work on a designated section. Approximately 4 million m³ of dredged soil to be retrieved. The Weser is a river in north-western Germany, Formed at Hann. Münden by the Fulda and Werra, it […]

  • 8 December 2016
    Business & Finance

    A U.S. Army Corps of Engineers project to remove more than 400,000 cubic yards of clean sediment from Marina del Rey’s harbor is set to begin on December 12, 2016. The five-month maintenance cleanup effort, undertaken by the dredge barge Heidi Renee, will be limited to the removal of sand accumulated at the north entry […]

  • 24 August 2016
    Business & Finance

    Work has started in the village of Skinningrove as part of the Environment Agency’s multi-million pound flood recovery program. Repair work in Skinningrove includes channel clearance and replacement and repairs to debris screens on the Kilton Beck, as well as improving access so they can be cleaned and maintained. The work started on Monday, August […]

  • 4 November 2015
    Business & Finance

    The U.S. Army Corps of Engineers, Savannah District, has announced the completion of the Fort Pulaski Shoreline Stabilization Project. The monthlong shore stabilization project used dredged material from the Savannah Harbor Navigation Project to restore a 1.5-mile section of beach along Cockspur Island’s north shore. Erosion over the past decade was threatening the park’s historic […]

  • 18 March 2013

    The Small Boat Harbor in Bethel began a month long dredging process to remove built up sediment. The Brown’s Slough entrance to the Kuskokwim River is closed. The Army Corp of Engineers has contracted with Denali Drilling out of Anchorage to dredge the harbor. “Dredging is essentially digging in water. So overtime sediment in the […]

  • 2 October 2013

    Flood protection of Carnarvon’s valuable horticultural industry is on track with the bulk of earthworks for the first two major levees nearing completion. Water Minister Terry Redman said the $60million Stage 2 Carnarvon flood mitigation project had progressed well since work began last November and was due to be finished by mid-2014. The Carnarvon horticultural […]

  • 18 April 2017
    Business & Finance, Project & Tenders

    The U.S. Army Corps of Engineers, Jacksonville District, has just announced that ongoing dredging work on the Banana River, known as Cut 13, will affect Canaveral Lock hours today. According to the Corps, dredging will occur along Canaveral Lock’s west approach wall requiring the lock to be closed 7AM to 11 AM and 12 PM to […]

  • 14 December 2011

    North Rhine-Westphalia (NRW) Economy Minister Harry K. Voigtsberger intends to press the federal German government to take cross-border infrastructure projects into account in implementing the national port concept. The minister made this clear during a parliamentary evening on the theme Transport and Logistics hosted recently by the NRW Economy Ministry and the Port of Rotterdam […]

  • 29 March 2018
    Business & Finance

    The Port of Kalama has submitted a request to modify their existing U.S. Army Corps of Engineers permit (NWP-1994-462/1) in order to provide additional in-water dredge material disposal sites and beach nourishment sites for their maintenance dredging operations. The existing Corps permit authorizes maintenance dredging at the terminals to -48 Columbia River Datum (CRD) with a 2-foot […]

  • 1 August 2016
    Business & Finance, Vessels

    The North Carolina Department of Transportation (NCDOT) recently took delivery of a new, fully customized cutter suction dredger. This piece of equipment, designed and built by DSC Dredge, was christened the Dredge Manteo in a ceremony held April 28, 2016, at the NCDOT State Shipyard in Manns Harbor, North Carolina. The 154-foot pipeline dredger will work […]

  • 26 January 2012

    The Panama Canal Authority (ACP) and North Carolina State Ports Authority (NCSPA) recently renewed their strategic alliance with the signing of a Memorandum of Understanding (MOU). The MOU, which is renewable for five years, was first signed in December 2010. The agreement reaffirms both entities’ dedication to generating new business and promoting an “all-water-route.” “The […]

  • 24 September 2014
    Business & Finance, Equipment, Technology

    The U.S. Army Corps of Engineers, Rivers Project Office, is announcing the temporary closure of the Two Rivers South Access Area in Rockport, IL. This access area will be closed from October 1-31, 2014 for dredging. Boats wishing to launch in this section of the river should use Two Rivers North Access Area to the […]

  • 11 April 2019
    Business & Finance, Project & Tenders

    Weeks Marine Inc. – working under the Northern Ocean County Coastal Storm Risk Management project –  is currently carrying out a program of beach replenishment works in Pt. Pleasant Beach (NJ). According to the Army Corps, the sand placement operations began on April 8, 2019. The anticipated completion date for the Pt. Pleasant Beach works is late May-early June. […]

  • 11 November 2016
    Business & Finance, Equipment, Technology

    The Cherry Grove Dredging Project, being conducted by Orion Marine’s two dredgers, is moving ahead. Earlier this week, one dredge worked in the ‘E Canal’ and another was several blocks down in the Minor Channel. This photo, just released by the City of North Myrtle Beach, was taken at the Minor Channel, east toward Lake […]

  • 16 February 2012

      Recently, CCCC Forth Harbor Engineering Co., Ltd. won the bid of the Haikou Port Xinhai Wharf Area Phase I, with bid-award value of RMB 438 million and construction period of 670 days. As a major harbor area that assumes the passenger and cargo vehicles’ Ro-Ro transport, the project is made up of nine 3000GTcargo-passenger […]

  • 1 September 2010
    Business & Finance

    In a visit to IHC Engineering Business (EB) on Tuesday 31 August 2010, local Labour MP, Alex Cunningham, (Stockton North), declared that the company which recently (31 May 2010) completed an order to build one of the world’s biggest marine pipe laying machines, represents the “future and the best of the past”. Local MP, Alex […]

  • 18 July 2012

    EPA has issued a Proposed Cleanup Plan Amendment for the cleanup of dioxin at the Centredale Manor Restoration Project Superfund Site in North Providence, R.I. Dioxins are toxic chemicals that naturally exist in the environment and can be released into the environment through forest fires, backyard burning of trash, certain industrial activities, and residue from […]

  • 12 January 2015
    Business & Finance, Equipment, Technology

    The MacArtney Underwater Technology Group has announced the inauguration of its fifth dedicated business unit in North America. Located in Jupiter, Florida, just north of West Palm Beach, the new MacArtney ‘Southeast Operations’ will cover a six-state area including Tennessee, North Carolina, South Carolina, Alabama, Georgia and Florida. Headed by General Manager, Lou Dennis, the […]

  • 13 January 2015
    Business & Finance, Equipment, Technology

    At the General Assembly Meeting of North Adriatic Ports Association (NAPA), held on 12th January in Trieste, the presidents, taking stock of the results achieved so far, reaffirmed the intention to continue common activities focused mainly on promotional and institutional field. During the general assembly, the ports signed the new Memorandum of Understanding in which […]

  • 4 September 2013
    Business & Finance

    The Lake Worth Inlet Feasibility Study proposes to deepen and widen the Federal channel from Lake Worth Inlet to the Port of Palm Beach. The Draft Feasibility Report and Environmental Impact Statement (EIS) has been revised as a result of comments received during the comment review period (including independent external peer review). All comments have […]

  • 19 December 2013
    Business & Finance

    Napa Ports, satisfied for infrastructural objective reached in the present European process for the adoption of the new Ten-T and CEF (Connecting Europe Facility), signed in Venice the Memorandum of Understanding in order to define a new strategic Master plan for ports development. The plan pinpoints infrastructural priority and needs in a common proposal to […]

  • 8 December 2017
    Business & Finance

    Port Canaveral has completed the deepening of the West Turning Basin, which now allows deeper draft access to the port’s container cargo facility operated by GT USA at North Cargo Berth 5 and 6. The 6-month project, worth $7.5 million, deepened the West Turning Basin to the authorized depth of -43 feet plus 2 feet additional […]

  • 18 September 2013

    U.S. Army Corps of Engineers continues to make progress on the north shore of the Indian River Inlet in Delaware. The Army Corps is pumping approximately half a million cubic yards of sand onto the north shore as part of Hurricane Sandy recovery efforts. The beach nourishment project involves dredging more than 500,000 cubic yards […]

  • 19 August 2019
    Business & Finance, Project & Tenders, Vessels

    North Norfolk District Council has just announced that the last load of sand for the Bacton to Walcott Sandscaping project was pumped at Walcott Sunday, 18 August. According to the Council, hopper dredger HAM 318 completed the sand nourishment work yesterday and is now sailing back to the Netherlands. They also added that following the […]