Search results for: pile driving

96 results

A list of search results

  • 17 November 2017
    Business & Finance, Project & Tenders

    The last pile has been put in place at Tacoma’s Husky Terminal Pier 4, according to the Northwest Seaport Alliance. Since awarding the contract to Manson Construction Company and launching the first phase of the project in May 2016, the construction is now more than halfway complete. “The last of the 1,245 piles on Pier 4 was […]

  • 30 August 2017
    Business & Finance, Project & Tenders

    The Haines Borough in Alaska has just released latest update on the Portage Cove Harbor Expansion project. According to the update, Pacific Pile & Marine has completed the harbor dredging and will begin installing the new breakwater. Pile driving work will begin at the entrance of the harbor and move south. “There will be times when […]

  • 16 December 2013
    Business & Finance, Equipment, Technology

    Construction activity continues on the foundation of the New NY Bridge with the ongoing installation of permanent piles. Excavation and preparation work for installation of permanent sound barriers continues along I-87 northbound/I-287 westbound in the area south of exit 10 in Rockland County. On Monday, Dec. 16, and Tuesday, Dec. 17, the northbound right-hand lane […]

  • 21 October 2013
    Business & Finance

    Tappan Zee Constructors, LLC (TZC) began formal construction of the New NY Bridge on Wednesday, October 16 with installation of the first permanent piles that will comprise the bridge’s foundation. Pile driving will be limited to the hours of 7 a.m. to 7 p.m. on weekdays and, occasionally, from 12 noon to 7 p.m. on […]

  • 21 August 2013
    Business & Finance

    Tappan Zee Constructors, LLC (TZC) will begin testing both static and lateral loads this week as part of its test pile program. These load tests are performed to ensure piles are capable of sustaining the design load of the new bridge. Testing will be conducted over a 40-hour period. Impact pile driving will continue this […]

  • 11 March 2020
    Business & Finance

    The $20 million redevelopment project of the Port Nelson’s Main Wharf North is progressing well with the demolition of the old wharf now completed. The next phase of the scheme is building the piles for the new concrete and steel berthing facility. Sheet piling behind the wharf will start this week with pile driving scheduled […]

  • 29 January 2020
    Business & Finance

    Starting February 15, property owners and contractors are banned for four months from dredging and excavating at Smith Mountain and Leesville lakes due to fish spawning, according to a news release from Appalachian Power. The policy is necessary to support fish population growth, including sunfish, catfish and variations of bass, said Dan Wilson, a fisheries […]

  • 9 August 2019
    Business & Finance

    The Canadian unit of the Belgium-based contractor BESIX has been awarded an LNG berth marine structure deal for the Shell-led LNG Canada project in Kitimat, British Columbia. BESIX Canada, together with its joint venture partner Vancouver Pile Driving (Vanpile), has been hired by the project’s EPC contractor JGC-Fluor JV. Works include the construction of a […]

  • 29 August 2018
    Business & Finance

    A berth expansion project at Port Charlottetown, aimed to extend the existing berth space by 270m and to allow for two vessels up to 330m to berth simultaneously, is officially underway. In order to complete the expansion, various stages of construction are required. The project consists of four additional mooring buoys and four additional breasting […]

  • 20 June 2018
    Business & Finance, Project & Tenders

    Cruise ships are one step closer to returning to Lyttelton Harbor, as construction begins on Lyttelton Port Company’s (LPC) cruise berth. The new cruise berth will be located between Cashin Quay and the entrance to the Inner Harbor. It will be the first custom-built cruise ship facility in New Zealand designed to accommodate the world’s […]

  • 3 May 2018
    Business & Finance

    The Steamship Authority has just released the latest update on their Woods Hole Ferry Terminal Reconstruction Project, saying that Jay Cashman, Inc. continues to work on the temporary dolphins.  The pile driving for the temporary dolphins has been completed and Cashman has begun welding the frames together. Cashman also continued work on the passenger platforms between […]

  • 20 September 2017
    Business & Finance

    The Department of Transport WA announced today that jetty construction works are underway at Mersey Point Shoalwater, Rockingham. According to the department, the works to construct a new jetty at Mersey Point are expected to be completed by 30 January 2018. “The works will take place Monday to Friday from 7:00 am to 5:00 pm, with provision […]

  • 18 August 2017
    Business & Finance

    Manson Construction Co. is rehabilitating the fender system for the Port of Redwood City Wharves 3 and 4, announced the port on its website today. According to the port, the works are planned for August 2017 through March 2018. “Derrick barge operations will utilize anchors and/or spuds to support pile driving and demolition along the […]

  • 27 May 2016
    Business & Finance

    The Long Beach City Council has approved the next phase of the Colorado Lagoon’s restoration, to further enhance the ecological value of the Lagoon through the creation of additional aquatic resources. The restoration project will establish new aquatic resources and essential fish habitat through balanced hydraulic dredging and filling of the Lagoon site. The floating […]

  • 25 May 2016
    Business & Finance

    AW Maritime has just released an update on the Portarlington Safe Harbor Redevelopment Project. The company is currently assisting Parks Victoria during the construction of the Portarlington scheme, having completed the detailed design of all maritime aspects of the development including breakwaters and marine structures. Current works involve the construction of rock breakwaters to the east and […]

  • 22 December 2015
    Business & Finance

    Environment Minister Mary Polak and Transportation and Infrastructure Minister Todd Stone have issued an environmental assessment certificate to Rio Tinto Alcan for the Terminal A Extension project in Kitimat. The decision was made after considering a review led by British Columbia’s Environmental Assessment Office. The ministers have issued the certificate with legally enforceable conditions that […]

  • 22 December 2015
    Business & Finance

    Contractors will begin driving test piles at the Northwest Seaport Alliance Terminal 5 in Seattle the first week of January. The installation will last through March. The pile driving and testing is part of the design phase of the terminal’s improvements. Test results could help reduce the final number of piles required and refine the depth of […]

  • 9 March 2015
    Business & Finance, Project & Tenders

    Reconstruction of the first 57 meter section of the Lyttelton Port of Christchurch (LPC) Cashin Quay 2 wharf has been completed, providing a second container vessel berth at the wharf for the first time since the February 2011 earthquake. The rebuilding of Cashin Quay 2, following earthquake damage, is being delivered in stages. By late April the new wharf […]

  • 12 January 2015
    Business & Finance, Equipment, Technology

    Coda Octopus Echoscope® Real-Time 3D sonar has been selected by Vale S.A. to produce dynamic underwater surveys during construction operations on the North Berth of Pier IV at the Ponta da Madeira Maritime Terminal in Sao Luis, Maranhao, Brazil. Vale S.A. is a global mining company with headquarters in Brazil and operations in over 30 […]

  • 29 October 2014
    Business & Finance

    Riverkeeper, Waterkeeper Alliance and Environmental Advocates of New York have filed a lawsuit against New York State officials, seeking to ensure that urgently needed federal Clean Water Act funds will not be illegally used to fund the new Tappan Zee Bridge construction project or for other ineligible projects in the future. The suit was filed […]

  • 30 June 2014
    Business & Finance, Project & Tenders

    Tappan Zee Constructors, LLC (TZC) will continue work on the New NY Bridge from Monday, June 30 through Thursday, July 3.  In addition, an enhanced marine law enforcement presence on the Hudson River  will enforce the rules of the Regulated Navigational Area (RNA), reminding recreational boaters to stay away from construction equipment. Mariners should be […]

  • 17 June 2014
    Business & Finance, Equipment, Technology

    Governor Andrew M. Cuomo said yesterday that the New York State Environmental Facilities Corporation (EFC) will make up to $511.45 million in low-cost loans to the New York State Thruway Authority for environmental protection and Hudson River restoration projects related to the New NY Bridge project to replace the Tappan Zee. Along with the $1.6 […]

  • 26 March 2014
    Business & Finance, Equipment, Technology

    Grant PUD Commissioners voted yesterday to accelerate plans for scheduled improvements to Wanapum reservoir boat launches during low-elevation conditions, pending regulatory approval. The Wanapum reservoir has been drawn down by about 26 feet since a fracture was discovered in one of Wanapum Dam’s spillway pier monoliths on Feb. 27. Under the low-water conditions, boat launches […]

  • 7 February 2014
    Business & Finance, Equipment, Technology

    First customer for the latest Richard Smalley 363MkII amphibious dredger is Barry Westby Groundworks of Broadway, Worcs . This updated design has a larger 63 kw ( 83.5 bhp) at 2,500 rpm water cooled diesel engine, lifting capacity increased by 20%, capable of loading a full 400 l bucket every time. All controlled by electric […]

  • 28 January 2014
    Business & Finance, Equipment, Technology

    The “I Lift NY” super crane began the last leg of its journey this week, completing its passage through the Panama Canal on Jan. 17 and making its way up the eastern seaboard. The super crane’s voyage began on Dec. 22, and early next month it is expected to arrive in the Port of New […]

  • 6 January 2014
    Business & Finance

    Normal operations are scheduled to resume today, as crews continue construction of the foundation of the New NY Bridge with the ongoing installation of permanent piles, according to newnybridge.com. Subsurface utility investigations will take place in Tarrytown this week. To facilitate this operation, the northbound right-hand lane of the New York State Thruway (I-87/I-287) near […]

  • 20 December 2013

    Luka Koper has commenced construction of a 6,840 m2 storage area behind berth 7C, at the head of the Pier I Container Terminal of the Port of Koper. This 8,390,000 euro (inclusive of VAT) investment – referred to as Dilatacija (Expansion) 2 and 3 in the project documentation – shall be capable of storing an […]

  • 20 December 2013

    The East Shores – Gladstone Coal Exporters Maritime Precinct project is progressing well, with construction of the waterfront boardwalk and viewing deck now underway. Pile-driving activities have now been completed at the $45M project, which is being delivered by Gladstone Ports Corporation (GPC) and Wiggins Island Coal Export Terminal (WICET), and the placement of concrete […]

  • 17 December 2013
    Business & Finance, Equipment, Technology

    J.F. Brennan Company, Inc. has been a marine professional since 1919 with a specialty in marine construction and environmental remediation for inland waterways throughout the United States. Headquartered in La Crosse, Wisconsin, J.F. Brennan works with both government agencies and private owners providing services such as dredging, diving, dam repairs, pile driving, railroad bridge repairs, […]