Picture of the Day: Working on the North Topsail Beach

Phase five of the North Topsail Beach (NC) shoreline restoration project continues according to schedule.

According to the latest update, work zone currently extends between 139 S Permuda Wynd and 310 Seashore Drive (approximately between Sta. 617+00 to Sta. 606+00).

Tigerhole Landscaping continued conducting rock picking operations within the constructed berm area between 3010 Island Drive and the north side of the Onslow County Beach Access No. 2, reported the Town of North Topsail Beach.

They will be in this area for approximately the next 3 to 5 days.

The contractor, Norfolk Dredging Company rock picker was last reported near 2nd Ave and 18th Ave.

 

Share this article

Follow Dredging Today

Events>

<< Mar 2020 >>
MTWTFSS
24 25 26 27 28 29 1
2 3 4 5 6 7 8
9 10 11 12 13 14 15
16 17 18 19 20 21 22
23 24 25 26 27 28 29
30 31 1 2 3 4 5

Navingo Career Event 2020

The Navingo Career Event is Europe’s biggest career event for the maritime,…

read more >

Jobs>

Looking to fill a job opening?

By advertising your job here, on the homepage of DredgingToday.com, you'll reach countless professionals in the sector. For more information, click below...

apply

Dredging jobs in Abu Dhabi at NMDC

National Marine Dredging Company “NMDC” aims to be the largest dredging player in the Arab’s Gulf region...

apply

Looking to fill a job opening?

By advertising your job here, on the homepage of DredgingToday.com, you'll reach countless professionals in the sector. For more information, click below....

apply