Dredging of Savannah Harbor Entrance Channel 25 Pct Complete

At the Georgia Ports Authority board meeting Monday, September 19th, Executive Director Griff Lynch updated the board on the progress of the Savannah Harbor Expansion Project.

During the meeting, Lynch said that to date, approximately 25 percent of the SHEP entrance channel dredging has been completed.

The $134.5 million contract for the deepening of the Savannah Harbor federal shipping channel was awarded to Great Lakes Dredge & Dock Company (GLDD) in early 2015.

The project, part of the SHEP, involves dredging of the entrance channel to a depth of 47 feet and represents the first step in deepening the 40 mile long shipping channel and harbor.

It is expected that the dredging operations will be completed by summer 2018.

Share this article

Follow Dredging Today

Events>

<< Apr 2020 >>
MTWTFSS
30 31 1 2 3 4 5
6 7 8 9 10 11 12
13 14 15 16 17 18 19
20 21 22 23 24 25 26
27 28 29 30 1 2 3

Navingo Career Event 2020

The Navingo Career Event is Europe’s biggest career event for the maritime,…

read more >

Jobs>

Dredging jobs in Abu Dhabi at NMDC

National Marine Dredging Company “NMDC” aims to be the largest dredging player in the Arab’s Gulf region...

apply

Looking to fill a job opening?

By advertising your job here, on the homepage of DredgingToday.com, you'll reach countless professionals in the sector. For more information, click below....

apply

Looking to fill a job opening?

By advertising your job here, on the homepage of DredgingToday.com, you'll reach countless professionals in the sector. For more information, click below...

apply