DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›Port Nelson: Calwell Slipway Cleanup Works Completed
Business & Finance

June 25, 2018 · about 8 years ago

Port Nelson: Calwell Slipway Cleanup Works Completed

New Zealand’s Port Nelson said in its latest announcement that Heron Construction has completed site disestablishment and restoration works at their Calwell Slipway, meaning that the project is now fully completed. “We have been successful in achieving the remediation targets. The target concentrati

1 minutes read
  • LinkedIn
  • X
  • Email

New Zealand’s Port Nelson said in its latest announcement that Heron Construction has completed site disestablishment and restoration works at their Calwell Slipway, meaning that the project is now fully completed.

“ We have been successful in achieving the remediation targets. The target concentrations for residual sediments remaining in the Calwell Slipway Basin was 270 mg/kg for Copper and 0.07mg/kg for Tbt, and these were deemed to be met when the 95% Confidence Limit of the rolling mean met these levels ,” Port Nelson said in its release.

“ At the conclusion of site works and validation sampling these remedial targets had been exceeded with a final result of 42mg/kg for Copper and 0.039mg/kg for Tbt .”

Additionally, more material was dredged than they initially projected with the final dredge volume being 32,516m³, and this meant the mudcrete produced and placed in the reclamation was 58,781T.

The second remedial objective was to restore navigability to the Calwell Slipway Basin which had not been dredged since 1984.

Post dredge hydrographic survey indicates that charted depths have been restored, and in many locations within the basin they have been exceeded, said Port Nelson in the official statement.

Check out this time-lapse capturing the remediation and reclamation process at the Calwell Slipway Basin from October 2017 to completion in June 2018:

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & Finance

Daily Dredging and Port Construction News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Dredging on Everett Harbor and Snohomish River begins soon
  2. 2Dravo wins Gioia Tauro dredging contract
  3. 3Aktau Port dredging kicks off
  4. 4Jan De Nul's TSHD Diogo Cão raises the bar in Vlissingen

Daily Dredging and Port Construction News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free