DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›IJmuiden July Update: Sinking Operations to Start in August
Business & Finance

July 14, 2018 · about 8 years ago

IJmuiden July Update: Sinking Operations to Start in August

Despite the delay in the construction of the IJmuiden sea lock reported this month, activities are continuing apace, Port of Amsterdam said in its latest release. According to the official announcement, July is devoted to construction work on the lock gate chamber of the outer head – the lock gate c

1 minutes read
  • LinkedIn
  • X
  • Email

Despite the delay in the construction of the IJmuiden sea lock reported this month, activities are continuing apace, Port of Amsterdam said in its latest release.

According to the official announcement, July is devoted to construction work on the lock gate chamber of the outer head – the lock gate chamber on the seaward side.

Also in July, OpenIJ will be continuing with the tensioning operation on the anchors of the lock chamber walls and will also be working on the Lock Operation Center – known by the acronym “SOC”.

Outer head lock gate chamber

Right now, OpenIJ is busy preparing for the sinking of the outer head lock gate chamber (the seaward side one).

The sinking operations are expected to start in August, according to the update.

Sinking is the preferred method to bring the lock gate chamber to its final vertical position.

At present, the underside of the floor of the lock gate chamber lies 5 meters below NAP (NAP is Normal Amsterdam Level – roughly Mean Sea Level). The lock gate chamber will be sunk another 18 meters to a final depth of approximately 23 meters below NAP.

After the lock gate chamber has been sunk to its final position, two more vertical layers will be constructed on top of the present walls (this means around 7.20 meters of extra height).

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & FinanceEquipmentTechnology

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Boskalis: Geopolitical tensions in the Middle East adversely impact activity levels
  2. 2Anaklia dredging project accelerates with two Jan De Nul TSHDs in the area
  3. 3VIDEO: Damen TSHD Kapuka gears up for sea trials
  4. 4Spotlight on Tuvalu Coastal Adaptation Project in Funafuti

Daily news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free