DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Infrastructure›Centerm expansion project – December update
Infrastructure

December 8, 2020 · about 5 years ago

Centerm expansion project – December update

The Port of Vancouver (BC) today released the latest update on their Centerm Expansion Project and ongoing works in the area. As reported, work in the water, on the terminal, and on the south shore continues in December. The land fill in the eastern expansion area continues to settle and will be rem

1 minutes read
  • LinkedIn
  • X
  • Email
Centerm expansion project – December update
Centerm

The Port of Vancouver (BC) today released the latest update on their Centerm Expansion Project and ongoing works in the area.

As reported, work in the water, on the terminal, and on the south shore continues in December.

The land fill in the eastern expansion area continues to settle and will be removed in January 2021. “We expect that the northeast perimeter dyke will be completed this month,” the port said in the update.

On the other hand, the perimeter dyke in the western expansion area is now complete. The infilling and preload placement in the lagoon will begin this month.

“We have closed the perimeter dyke in the western expansion area, and infilling and preload placement in the new lagoon will begin this month,” the port said. “Some of the preload material currently sitting on top of the land created in this area has been pushed northward to start to fill in the lagoon.”

An interesting fact, approximately 9,000 cubic meters of sand will be transported to the project site each day. That’s three, eight-hour round trips a day for the Fraser River Pile and Dredge 309 dredging vessel. Once at the terminal, the material is pumped into the lagoon by a large pipe attached to the vessel.

The Centerm Expansion Project, delivered by Centennial Expansion Partners (CXP), is set to be complete by the end of 2021.

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

InfrastructurePorts & Logistics

Daily dredging and port construction news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1BREAKING NEWS: Asia's largest TSHD begins Binhai Port dredging program
  2. 2Dominican Republic: The Netherlands, INTEC address climate change adaptation solutions
  3. 3CHEC builds breakwater at Apia Port on Samoa
  4. 4EXCLUSIVE: TSHD Teunis Huibertus gears up for Eemshaven job

Daily dredging and port construction news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free