DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Operations & Maintenance›Island construction project in Pigs Eye Lake starting this week
Operations & Maintenance

June 8, 2022 · about 4 years ago

Island construction project in Pigs Eye Lake starting this week

A U.S. Army Corps of Engineers, St. Paul District contractor, LS Marine of Inver Grove Heights, Minnesota, will begin island construction work in Pigs Eye Lake this week. USACE, in partnership with Minnesota’s Ramsey County, awarded a $14.7 million contract last June to LS Marine, Inc., to restore h

2 minutes read
  • LinkedIn
  • X
  • Email
Island construction project in Pigs Eye Lake starting this week
USACE

A U.S. Army Corps of Engineers, St. Paul District contractor, LS Marine of Inver Grove Heights, Minnesota, will begin island construction work in Pigs Eye Lake this week.

USACE, in partnership with Minnesota’s Ramsey County, awarded a $14.7 million contract last June to LS Marine, Inc., to restore habitat on Pigs Eye Lake, located in upper Pool 2 of the Mississippi River a few miles from downtown St. Paul, Minnesota.

The contractor plans to beneficially reuse approximately 400,000 cubic yards of dredged material, or river sand, from the Pine Bend Island placement site to build six islands within the lake.

The initial construction will focus on building the island foundations and will largely be done underwater via hydraulic material placement. Construction is expected to crest the water surface later this year.

Once complete, the project will enhance and restore backwater habitat by creating island and wetland features for birds and fish. The project will also improve the water quality by reducing wind fetch.

The project features include island construction with sand benches, marsh habitat restoration and terrestrial plantings. The total project footprint will be approximately 40 acres and will provide benefits to more than 600 acres of Pigs Eye Lake and the surrounding habitat.

According to the Corps, heavy construction equipment will be used to place the material on the islands and boaters are asked to use caution if they are in the area as the lake will be an active construction site. Construction is expected to continue through November this year and will resume next spring with the final topsoil placement and vegetation planting.

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Operations & Maintenance

Daily Dredging and Port Construction News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Skanska builds new homeport pier at Naval Station Newport
  2. 2Ecocoast, Xylem partnership strengthens turbidity monitoring for GCC dredging projects
  3. 3Seaward Marine wins $15.2M Virginia Beach contract
  4. 4BREAKING NEWS: Renewed Afsluitdijk opens, Van Oord says

Daily Dredging and Port Construction News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free