The USACE Jacksonville District recently joined Palm Beach County and the City of Delray Beach to announce the kickoff of the Delray Beach Segment of the Palm Beach County Shore Protection Project – with major renourishment work beginning January 2026. Following the severe impacts of the 2022 hurric

Harwich Haven Authority (HHA) said that they will be partially closing the historic Ha’penny Pier in Harwich to members of the public from January 5 to allow essential maintenance works to take place. The closure follows recent repair work, carried out by the Authority, which found additional deteri

Royal IHC has just delivered another cutter suction dredger (CSD) Beaver 65 to its customer. “Even during the Christmas and New Year period, we continue to support our customers, completing the delivery of a beautiful Beaver 65 just before year-end,” said Cees Devries, commissioning engineer at Roya

Around 75 pct of the dredging work for the third phase of the Hulhumale’ development project has now been completed, the Maldives Airports Company Limited (MACL) said. Housing Development Corporation (HDC) added that these operations are progressing according to schedule, with two trailing suction h

The Provincial Government of Pangasinan (PGP), led by Governor Ramon V. Guico III, initiated the River Rehabilitation and Flood Mitigation Project with a dredging operation at the Limahong Channel in Lingayen on December 24. According to the Government, the project targets river mouths clogged with

Dredging operations are underway at the Kuryk Port on the Caspian Sea in Kazakhstan. The dredging program is set to to enhance the depth of the port and its access channel to 5 meters, facilitating year-round navigation and supporting the growth of transit flows along the Middle Corridor. Dredging o

The City of North Myrtle Beach said that the work on their latest beach nourishment project is in full swing. Under the plan, Great Lakes Dredge and Dock Company (GLDD) will first pump sand at the north end of the project area and proceed southward over an estimated 59-day period, spanning December

Maldives Airports Company Limited (MACL) has just released the latest update on the Rasmalé land reclamation project. So far, 41 hectares of new land have been successfully reclaimed, representing 30% overall progress. Rasmalé, also known as the Maldives Eco City, is a groundbreaking project located

The USACE New York District has partnered with New York University Tandon School of Engineering to provide graduate students with real-world project management experience through the U.S. Merchant Marine Academy’s (USMMA) Seawall Rehabilitation Project. Earlier this month, members of the District’s

Sarasota County has started a multiphase dredging project along Phillippi Creek to address flooding issues during major storms. In the following video, Sarasota County Stormwater Director Ben Quartermaine provides an update on Phase 1 (High-Spot Dredging) of the Phillippi Creek Dredge Project. This

Construction is complete on a rock weir structure that will help reduce outdraft conditions at Lock and Dam 7, located near La Crescent, Minnesota, the USACE St. Paul District said. USACE had identified Lock and Dam 7 as one of the most dangerous lock sites on the river, and after two years of plann

BCI Minerals Limited has secured all primary approvals from the Commonwealth and Western Australian Governments to enable offshore placement of material generated from its dredging program at the Cape Preston West Port in accordance with BCI’s optimized dredging methodology for the Mardie Salt Opera

The Town of Oak Island has released another update on its $33 million beach renourishment project, saying that the works will continue throughout the Town’s holiday closures. Last week, officials said that the project had reached one-third completion. This week, crews will return to the completed st

Rock work on a new 460-metre northern breakwater at Bunbury’s Casuarina Boat Harbor is complete, making way for further development on the waterfront, Transport WA said. Completion of the breakwater rock structure followed the dredging of its seabed footprint in late 2024 and the relocation of more