DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›News›USA: Corps Awards Boston Harbor Rock Removal Contract
News

July 19, 2012 · about 14 years ago

USA: Corps Awards Boston Harbor Rock Removal Contract

Rock removal from portions of the 40-foot deep Main Ship Channel in the Boston Harbor Federal Navigation Project in Boston, Mass., will be conducted under the terms of a $2,231,250.00 contract issued recently by the U.S. Army Corps of Engineers, New England District. Work will be accomplished by Bur

1 minutes read
  • LinkedIn
  • X
  • Email

Rock removal from portions of the 40-foot deep Main Ship Channel in the Boston Harbor Federal Navigation Project in Boston, Mass., will be conducted under the terms of a $2,231,250.00 contract issued recently by the U.S. Army Corps of Engineers, New England District.

Work will be accomplished by Burnham Associates, Inc., of Salem, Mass. The project is scheduled to start on or about Aug. 1, 2012 and be completed by about Sept. 30, 2012. The contract was awarded on July 16, 2012.

“ The project consists of the removal of rock/ledge from 7 locations in the Main Ship Channel of Boston Harbor ,” said Project Manager Mike Keegan, of the Corps’ New England District, Programs and Project Management Division in Concord, Mass. “ The rock that is removed from the channel will be placed at the rock reef portion of the Massachusetts Bay Disposal Site located approximately 20 miles offshore .”

Borings have been taken at the locations and rock testing performed. The contractor will drill and blast the rock to fracture it and it then will be removed with a mechanical clam shell dredge.

The project will be managed by the U.S. Army Corps of Engineers, New England District. All work will be accomplished under the supervision of a Corps of Engineers Quality Assurance Representative to assure compliance with contract requirements.

[mappress]

Dredging Today Staff, July 20, 2012; Image: ec.gc.ca

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

News

Daily dredging and port construction news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1PHOTO OF THE DAY: Argentina dredges its canals before El Niño
  2. 2Høj Nordic completes Schleswig-Holstein annual dredging
  3. 3Oceanside Harbor's channel dredging about to begin
  4. 4HERBOSCH-KIERE's Atlantis wraps up work at Dumping Area 42

Daily dredging and port construction news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free