DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›Panama Canal Completes Culebra Cut Dredging
Business & Finance

March 6, 2013 · about 13 years ago

Panama Canal Completes Culebra Cut Dredging

The Panama Canal Authority (ACP) has completed the dredging to deepen and widen the navigational channels along Culebra Cut as part of the Expansion Program. This marks another important milestone for the Panama Canal expansion. The dredging works started in March 2008, with the drilling by Panama C

2 minutes read
  • LinkedIn
  • X
  • Email

The Panama Canal Authority (ACP) has completed the dredging to deepen and widen the navigational channels along Culebra Cut as part of the Expansion Program. This marks another important milestone for the Panama Canal expansion.

The dredging works started in March 2008, with the drilling by Panama Canal personnel on board of the drill barge Baru.

“ This important achievement fills with pride each man and woman that works within the organization,” Panama Canal Administrator Jorge L. Quijano said . “ Gradually, we are completing all the projects that make up the Expansion Program.”

Culebra Cut is an area of difficult access due to the type of material and being the narrowest portion of the Canal’s navigational channel. ACP equipment was used for this project, including the dredges Mindi, Rialto M. Christensen and Quibian I, and the drill barges Thor and Baru.

In addition, contracted equipment was also used: the dredge II Principe, property of Belgian company Jan de Nul Group, and the dredge Cornelius, property of the Netherlands-based company Royal Boskalis Westminster N.V.

A total of 3.2 million cubic meters were removed during the deepening of Culebra Cut.

A week ago, the Expansion Program achieved another milestone, when the first million cubic meters of concrete were poured in the locks construction site on the Atlantic side. This represents 1,800 cubic meters of reinforced concrete poured in the wall of the southeast wing, at the point where the vessels will enter the locks from Gatun Lake.

[mappress]

Press Release, March 7, 2013

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & Finance

Daily dredging and port construction news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1PHOTO OF THE DAY: Argentina dredges its canals before El Niño
  2. 2Høj Nordic completes Schleswig-Holstein annual dredging
  3. 3Oceanside Harbor's channel dredging about to begin
  4. 4HERBOSCH-KIERE's Atlantis wraps up work at Dumping Area 42

Daily dredging and port construction news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free