DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›USA: Army Corps Presents Sawpit Creek Dredging Plan
Business & Finance

March 9, 2013 · about 13 years ago

USA: Army Corps Presents Sawpit Creek Dredging Plan

U.S. Army Corps of Engineers has introduced a plan for the Sawpit Creek maintenance dredging program. The project includes maintenance dredging of approximately 591,000 cubic yards (cy) of material from the AIWW channel and settling basins in Cuts 24-26A, 27, 27A, 27C; and adjoining advance maintena

1 minutes read
  • LinkedIn
  • X
  • Email

U.S. Army Corps of Engineers has introduced a plan for the Sawpit Creek maintenance dredging program.

The project includes maintenance dredging of approximately 591,000 cubic yards (cy) of material from the AIWW channel and settling basins in Cuts 24-26A, 27, 27A, 27C; and adjoining advance maintenance areas in the waters of Sawpit Creek, the Amelia River, and Nassau Sound.

The majority of the excavated material, 578,000 cy, will be placed on the Amelia Island State Park beach disposal site and is included within the base of the contract. The pumping distance between dredging areas and beach placement ranges from 4.0 miles to 1.5 miles.

The material from Cut-27, totaling approximately 13,000 cy, is being included as an option to this contract. The material within this reach is not beach compatible and cannot be placed on Amelia Island State Park. It will be placed in DMMA DU-2 which lies adjacent to Cut-26A and Cut-27. If this option is exercised, preparation of the DMMA-DU2 site will also be included in the project work.

The period of performance consists of the Base (121 calendar days) plus Option 1 (32 calendar days) for a total period of performance of 153 calendar days.

Magnitude of construction is between $5,000,000.00 and $10,000,000.00.

More info

[mappress]

Source: fbo.gov; March 10, 2013

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & Finance

Daily dredging and port construction news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1PHOTO OF THE DAY: Argentina dredges its canals before El Niño
  2. 2Høj Nordic completes Schleswig-Holstein annual dredging
  3. 3Oceanside Harbor's channel dredging about to begin
  4. 4HERBOSCH-KIERE's Atlantis wraps up work at Dumping Area 42

Daily dredging and port construction news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free