DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›USA: Draft Feasibility Report for Scribner Project Available for Review
Business & Finance

August 22, 2013 · about 13 years ago

USA: Draft Feasibility Report for Scribner Project Available for Review

A draft feasibility report and environmental assessment for stream bank restoration near Scribner, Neb. is currently available for public review. The report identifies alternatives to provide stream bank protection to prohibit rapid erosion on the east bank of the Elkhorn River, Dodge County, Neb. P

2 minutes read
  • LinkedIn
  • X
  • Email

A draft feasibility report and environmental assessment for stream bank restoration near Scribner, Neb. is currently available for public review. The report identifies alternatives to provide stream bank protection to prohibit rapid erosion on the east bank of the Elkhorn River, Dodge County, Neb. Public infrastructure being protected includes County Road F and the bridge.

“ The draft feasibility report and environmental assessment is the result of a comprehensive study conducted by the Corps in cooperation with the Lower Elkhorn Natural Resources District who is the project sponsor, Dodge County Roads Department, and the city of Scribner, ” said Gwyn Jarrett, project manager . “ The study was carried out under Section 14 of the Flood Control Act of 1946, as amended.”

Section 14 provides the Corps with authority to study, adopt, and construct emergency stream bank and shoreline protection projects to protect public highways and bridges, other public works, and nonprofit public services such as churches, hospitals, and schools and other non-profit facilities offering public services.

BACKGROUND

The Elkhorn River is a meandering stream with extremely flat gradients and very small channel capacities in relation to its drainage area. Rainfall in the spring often combines with annual plains snowmelt to produce floods that exceed the Elkhorn’s channel capacities and spread onto the broad floodplain. As a result, rapid erosion, which is occurring along the stream bank, is threatening the County Road F Bridge including the road approach and bridge abutments.

Alternatives outlined in the draft report include spur dikes, stone toe revetment, and sheet pile walls. Benefits of the project would include preserving an important farm-to-market route between Scribner and its market area on the east side of the Elkhorn River, and avoiding a costly bridge repair over the Elkhorn River.

[mappress]

Press Release, August 23, 2013

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & Finance

Daily dredging and port construction news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1PHOTO OF THE DAY: Argentina dredges its canals before El Niño
  2. 2Høj Nordic completes Schleswig-Holstein annual dredging
  3. 3Oceanside Harbor's channel dredging about to begin
  4. 4HERBOSCH-KIERE's Atlantis wraps up work at Dumping Area 42

Daily dredging and port construction news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free