DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›USA: Officials Seek Comments on Main Ditch 6 Levee Plan
Business & Finance

September 1, 2013 · about 13 years ago

USA: Officials Seek Comments on Main Ditch 6 Levee Plan

A draft environmental assessment for Public Law 84-99 levee rehabilitation construction at the Main Ditch 6 levee near Hamburg, Iowa is currently available for public review. Rehabilitation construction will consist of in-line repairs to bring the levee back to pre-flood conditions. This draft EA is

2 minutes read
  • LinkedIn
  • X
  • Email

A draft environmental assessment for Public Law 84-99 levee rehabilitation construction at the Main Ditch 6 levee near Hamburg, Iowa is currently available for public review. Rehabilitation construction will consist of in-line repairs to bring the levee back to pre-flood conditions.

This draft EA is consistent with the National Environmental Policy Act of 1969, as amended, the Council on Environmental Quality’s regulations for implementing NEPA (40 CFR 1500-1508), the Corps’ regulations for implementing NEPA (33 CFR 325 and Engineering Regulation 200-2-2), PL 84-99, and other applicable environmental laws and regulations.

BACKGROUND

The Main Ditch 6 levee protecting the city of Hamburg, Iowa came under major risk when the nearby L-575 levee breached west of town during the 2011 flood. Due to the breach and rising waters, the Main Ditch 6 levee was raised a total of eight feet to a final elevation of 919 feet mean sea level. The Main Ditch 6 emergency levee system was subjected to a sustained period of high water levels and several rounds of severe storms.

Damages were sustained to the entire levee cross section, closure structures, and all drainage structures. The levee system also experienced seepage.

As required by the PL 84-99 program, the city of Hamburg, in June 2013, began removing the temporary levee fortifications that were constructed during the flood. Once the temporary fortifications are removed, the Corps will begin repairing remaining drainage and closure structures, excavating ditch sedimentation, placing topsoil, and seeding. Repairs are expected to begin after September 2013. Following all construction, the levee system will be restored to pre-disaster conditions.

[mappress]

Press Release, September 2, 2013

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & Finance

Daily dredging and port construction news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1PHOTO OF THE DAY: Argentina dredges its canals before El Niño
  2. 2Høj Nordic completes Schleswig-Holstein annual dredging
  3. 3Oceanside Harbor's channel dredging about to begin
  4. 4HERBOSCH-KIERE's Atlantis wraps up work at Dumping Area 42

Daily dredging and port construction news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free