DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›USA: Miami Harbor Deepening Project Kicks Off
Business & Finance

November 20, 2013 · about 12 years ago

USA: Miami Harbor Deepening Project Kicks Off

The U.S. Army Corps of Engineers, Jacksonville District, began dredging operations yesterday on the Miami Harbor Deepening Project. In a collaborative effort with the PortMiami, Miami-Dade County, the contract for the Miami Harbor Deepening project was awarded to the Great Lakes Dredge & Dock Compan

2 minutes read
  • LinkedIn
  • X
  • Email

The U.S. Army Corps of Engineers, Jacksonville District, began dredging operations yesterday on the Miami Harbor Deepening Project.

In a collaborative effort with the PortMiami, Miami-Dade County, the contract for the Miami Harbor Deepening project was awarded to the Great Lakes Dredge & Dock Company, LLC in May 2013, for a total contract amount (Base plus Option A and Option B) of $205,797,456.

The Base phase includes deepening existing Federal navigation channels in Cuts 1 and 2, primarily from 44 feet to 52 feet deep, and widening the outermost portion of Cut 1, resulting in approximately 2.1 million cubic yards of dredge material being excavated from the Federal channel. The contractor will relocate coral, create artificial reef, and construct a seagrass mitigation site in this phase using some of the excavated material.

Material not used to create the mitigation sites will be transported to the Ocean Dredged Material Disposal Site. The estimated construction duration is approximately two years.

The Corps anticipates exercising Option A in December 2013 and Option B in late January 2014. Option A covers the dredging of Cut-3 Station 0+00 to Station 12+00 and Fisherman’s Channel from Station 17+00 to the end of the Lummus Island Turning Basin, as well as dredging the berthing areas adjacent to these reaches; and, Option B covers the dredging of Cut-3 Station 12+00 to Fisherman’s Channel Station 17+00 as well as dredging the berthing areas adjacent to these reaches.

[mappress]

Press Release, November 21, 2013

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & Finance

Daily dredging and port construction news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1PHOTO OF THE DAY: Argentina dredges its canals before El Niño
  2. 2Høj Nordic completes Schleswig-Holstein annual dredging
  3. 3Oceanside Harbor's channel dredging about to begin
  4. 4HERBOSCH-KIERE's Atlantis wraps up work at Dumping Area 42

Daily dredging and port construction news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free