DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›Corps Assists Snohomish County with Raising Temporary Berm (USA)
Business & Finance

April 16, 2014 · about 12 years ago

Corps Assists Snohomish County with Raising Temporary Berm (USA)

The U.S. Army Corps of Engineers, Seattle District, has nearly completed construction of the temporary berm within the SR530 slide area. Though the berm is complete in length, construction efforts have now shifted to raising the berm an additional foot ahead of predicted heavy rainfall. The addition

1 minutes read
  • LinkedIn
  • X
  • Email

The U.S. Army Corps of Engineers, Seattle District, has nearly completed construction of the temporary berm within the SR530 slide area. Though the berm is complete in length, construction efforts have now shifted to raising the berm an additional foot ahead of predicted heavy rainfall.

The additional height is expected to help reduce potential flooding risks, and the Corps is maintaining close coordination and communication with Snohomish County officials as recovery workers continue to search the area.

The 3,000-linear-foot berm, made from 20,000 tons of rock, gravel and earthen materials, was constructed under difficult conditions. Work on the berm began only a week ago. It was built through areas of deep water and has been accessible only via a gravel road by a USACE team and workers from Snohomish County public works.

The temporary berm is located near mile post 37 at C Post Road and is used to help recovery workers pump out water from a search area, reduce flood impacts and prevent near-term flooding of State Route 530. The berm is a temporary flood prevention measure designed to prevent flooding under normal spring runoff conditions.

[mappress]

Press Release, April 17, 2014

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & FinanceEquipmentTechnology

Daily dredging and port construction news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1PHOTO OF THE DAY: Argentina dredges its canals before El Niño
  2. 2Høj Nordic completes Schleswig-Holstein annual dredging
  3. 3Oceanside Harbor's channel dredging about to begin
  4. 4HERBOSCH-KIERE's Atlantis wraps up work at Dumping Area 42

Daily dredging and port construction news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free