DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›USACE St. Paul District Urges Early Planning for Permits (USA)
Business & Finance

May 11, 2014 · about 12 years ago

USACE St. Paul District Urges Early Planning for Permits (USA)

The U.S. Army Corps of Engineers, St. Paul District, encouraged project planners to carefully plan projects in Minnesota and Wisconsin requiring Corps permits. The Corps of Engineers also reminds planners that the majority of proposed projects and activities in and around waters and wetlands require

1 minutes read
  • LinkedIn
  • X
  • Email

The U.S. Army Corps of Engineers, St. Paul District, encouraged project planners to carefully plan projects in Minnesota and Wisconsin requiring Corps permits.

The Corps of Engineers also reminds planners that the majority of proposed projects and activities in and around waters and wetlands require Corps authorization.

The Corps urges planners to submit permit applications as soon as possible in the planning process. The Corps suggests submitting applications for work in waters or wetlands associated with projects, such as roads, utilities or development, at least one year prior to planned construction.

Currently, timeframes for general permit decisions, those with impacts generally less than 0.5 acres are averaging 85 days. Timeframes for individual permit decisions, which include letters of permission, range from 4 months to more than a year, but are currently averaging around 8 months.

The district’s regulators are working through issues related to sequestration, increased construction activities in the two states and other constraints that have significantly impacted the timeframes within which the Corps can process permit applications. These limitations are also affecting timeframes for other actions, such as jurisdictional determinations and wetland delineation report reviews.

[mappress]

Press Release, May 12, 2014

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & FinanceEquipmentTechnology

Daily dredging and port construction news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1PHOTO OF THE DAY: Argentina dredges its canals before El Niño
  2. 2Høj Nordic completes Schleswig-Holstein annual dredging
  3. 3Oceanside Harbor's channel dredging about to begin
  4. 4HERBOSCH-KIERE's Atlantis wraps up work at Dumping Area 42

Daily dredging and port construction news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free