DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›Beach Recharge to Begin Earlier Than Expected
Business & Finance

November 25, 2014 · about 12 years ago

Beach Recharge to Begin Earlier Than Expected

A highly anticipated stage of the £36 million Clacton and Holland on Sea Coastal Protection Scheme started yesterday, with the first beach recharge to create new sand and shingle beaches. The recharge hails an exciting new stage in the project, as the beaches start to take shape. The hopper dredger

2 minutes read
  • LinkedIn
  • X
  • Email

A highly anticipated stage of the £36 million Clacton and Holland on Sea Coastal Protection Scheme started yesterday, with the first beach recharge to create new sand and shingle beaches. The recharge hails an exciting new stage in the project, as the beaches start to take shape.

The hopper dredger vessel ‘Causeway’ has sailed to the Essex coast and is in the process of pumping sand and shingle material on to the newly created beach areas between the fishtail groynes. The 800m long sinker pipe constructing the new beaches has been sailed over separately and attached to the ship to begin work.

The material for the recharge has been taken from 19km out at sea in a designated dredging site. Once in place, the material will then be profiled by bulldozers.

The Cypriot vessel will make approximately four trips per day and each beach will take approximately one week to construct (weather dependent).

Hundreds of fascinated people have been venturing to the Holland Haven end of the scheme where phase one of the project has been taking place.

Work on building the first of the eight new beaches in phase one will continue until the end of December 2014. The team will then resume in March 2015 in better weather, to complete phase two of the scheme running to Clacton Pier.

The main contractor for the scheme is VBA Joint Venture Limited, with the program being project managed by Mott MacDonald.

[mappress mapid=”19353″]

Press Release

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & FinanceEquipmentTechnology

Daily Dredging and Port Construction News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Kazakhstan, Jan De Nul discusses cooperation perspectives, spotlight on dredging
  2. 2Greatham North East flood alleviation scheme gets OK
  3. 3Gator Dredging nabs Banana River dredging deal
  4. 4EXCLUSIVE: Doca dos Bacalhoeiros dredging kicks off

Daily Dredging and Port Construction News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free