DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›GLDD Kicks Off Duval County Shore Protection Project
Business & Finance

September 19, 2016 · about 10 years ago

GLDD Kicks Off Duval County Shore Protection Project

The U.S. Army Corps of Engineers, Jacksonville District, has just announced that the Duval County Shore Protection Project is officially underway with dredge Terrapin Island pumping sand at the south end of Jacksonville Beach. The Corps contractor, Great Lakes Dredge & Dock Company will place sand o

2 minutes read
  • LinkedIn
  • X
  • Email

The U.S. Army Corps of Engineers, Jacksonville District, has just announced that the Duval County Shore Protection Project is officially underway with dredge Terrapin Island pumping sand at the south end of Jacksonville Beach.

The Corps contractor, Great Lakes Dredge & Dock Company will place sand on seven miles of eroded beaches, including Jacksonville, Neptune and a portion of Atlantic Beach.

The beach renourishment project will widen the beach berm between 20 to 60 feet, and raise the elevation of the beach by about 3 to 5 feet.

Initial sand placement started last week around 37th Avenue South, and will progress southward to the County Line, and then northward from 37th Avenue. The contractor will establish four or five subline/pipeline “landings” on the shore in Jacksonville Beach, one in Neptune and two landings in Atlantic Beach. GLDD will pump sand through the pipeline toward the south, and then toward the north, from each landing site.

Project completion is set for November 2016, barring unforeseen events.

The Duval County project was initially constructed in 1978-80 and since then, five principal renourishments occurred (1985-87, 1991, 1995, 2005, and 2011) in addition to periodic placement of sand dredged from navigation projects. Beach renourishment occurs about every five to six years to maintain beaches as part of the project.

The Corps awarded the 2016 construction contract June 28 to Great Lakes Dredge & Dock for $13,572,170. The renourishment is funded in partnership with the City of Jacksonville, Florida Department of Environmental Protection, and Duval County; 38.4 percent locally and 61.6 percent federally funded.

[mappress mapid=”23006″]

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & FinanceProject & TendersVessels

Daily Dredging and Port Construction News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Canal & River Trust: Gloucester Docks dredging budget doubled
  2. 2USACE completes Lorain Harbor dredging
  3. 3PHOTO OF THE DAY: TSHD Albatross gears up for South Port job
  4. 4Port of Natal wraps up first phase of dredging program

Daily Dredging and Port Construction News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free