DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›GLDD Completes First Phase of John Redmond Reservoir Dredging
Business & Finance

October 28, 2016 · about 10 years ago

GLDD Completes First Phase of John Redmond Reservoir Dredging

The Kansas Water Office (KWO) announced yesterday that the first phase of dredging at John Redmond Reservoir is complete. Great Lakes Dredge and Dock (GLDD) began dredging operations this past May. The project is the first of its kind in the nation with a non-federal entity dredging sediment from a

2 minutes read
  • LinkedIn
  • X
  • Email

The Kansas Water Office (KWO) announced yesterday that the first phase of dredging at John Redmond Reservoir is complete.

Great Lakes Dredge and Dock (GLDD) began dredging operations this past May.

The project is the first of its kind in the nation with a non-federal entity dredging sediment from a U.S. Army Corps of Engineers (USACE) reservoir.

Three million cubic yards of sediment was removed from the reservoir and placed in confined disposal facilities on USACE land and private property. These disposal sites will be returned to the preferred use of the respective landowners after dewatering.

“ In 2012, we started the planning process to conduct this large-scale dredging project to restore water supply storage at John Redmond ,” said Director of KWO, Tracy Streeter . “ This project was vital for the area. The reservoir is a supply source to 19 communities and six industrial users, including Wolf Creek Nuclear Operating Station. ”

The removal of sediment has helped to ensure an adequate water supply to meet the citizens’ demand in the future. Unfortunately past drought has shown the removal of three million yards will not solve all of the problems with the aging reservoir to help restore water supply storage lost to sedimentation.

“ Additional work in the watershed above John Redmond to reduce the sedimentation rate, evaluation of other waters supplies as well as future restoration work to remove sediment within the reservoir is still necessary to ensure future water supply demand is met through the year 2045 in the Neosho River basin, ” Streeter said.

More information and details about the project will be shared at the upcoming Governor’s Water Conference on November 14-15 in Manhattan, Kansas including a panel discussion involving Bryan Taylor, USACE –Tulsa District, Stan Ekren – GLDD and Matt Unruh – KWO Dredging Project Manager.

[mappress mapid=”23189″]

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & FinanceProject & Tenders

Daily Dredging and Port Construction News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Jan De Nul's TSHD Diogo Cão raises the bar in Vlissingen
  2. 2Skanska builds new homeport pier at Naval Station Newport
  3. 3Ecocoast, Xylem partnership strengthens turbidity monitoring for GCC dredging projects
  4. 4Seaward Marine wins $15.2M Virginia Beach contract

Daily Dredging and Port Construction News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free