DredgingToday
  • Capital Dredging
  • Maintenance Dredging
  • Land Reclamation
  • Port Expansion
  • Coastal Protection
  • More News
JobsNewsletter
DredgingToday logo

Your trusted source for global dredging news, part of the Navingo network.

Topics
  • Authorities & Government
  • Beach Nourishment
  • Berth Expansion
  • Breakwater Construction
  • Breakwater Construction & Repair
Network
  • Dredging Today
  • NavalToday
  • Offshore Wind
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report Your News
  • Privacy Policy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›Dismal Swamp Canal Dredging About to Begin
Business & Finance

March 6, 2019 · about 7 years ago

Dismal Swamp Canal Dredging About to Begin

The U.S. Army Corps of Engineers is set to begin Dismal Swamp Canal dredging early next week – roughly a year ahead of schedule due to lingering impacts from Hurricane Matthew in 2016. USACE Norfolk District will manage the maintenance dredging project in an effort to eliminate shoaling while enhanc

2 minutes read
  • LinkedIn
  • X
  • Email

The U.S. Army Corps of Engineers is set to begin Dismal Swamp Canal dredging early next week – roughly a year ahead of schedule due to lingering impacts from Hurricane Matthew in 2016.

USACE Norfolk District will manage the maintenance dredging project in an effort to eliminate shoaling while enhancing safe navigation and local commercial interests.

The Dismal Swamp Canal, which receives water from a feeder ditch connected to Lake Drummond, runs from Deep Creek in Chesapeake to South Mills, North Carolina. Material often collects at the intersection of the canal and ditch entrance.

“ That decreases the maintained depth to less than the 6 feet required for safe navigatio n,” said Joel Scussel, Norfolk District’s Atlantic Intracoastal Waterway project manager .

“ The Dismal Swamp Canal is authorized to a depth of 9 feet, but we maintain to a depth of 6 feet because of limited commercial traffic there. The area where we are dredging has a high shoaling rate, so we are actually dredging to 10 feet. That way, we don’t end up dredging every year, ” continued Joel Scussel.

He also added that dredging was last done here in 2015. It’s normally carried out on a five-year cycle, but Matthew deposited a large amount of material in the canal and pushed the time frame up.

“ We try to do dredging now due to the minimum canal traffic this time of year, ” Scussel said. “ The vessels that use the canal do have an economic impact to Elizabeth City, North Carolina .”

The $845,000 contract was awarded to Petersen Companies Inc. out of Minocqua, Wisconsin. It includes nearly $300,000 in upland placement-site repairs, which started at the end of January.

Scussel concluded that the maintenance dredging, expected to be completed by the start of April, will remove about 30,000 cubic yards of shoaling from the Dismal Swamp Canal.

Reach the DredgingToday industry in one go!

DredgingToday is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow DredgingToday on:

Filed under

Business & Finance

Daily dredging and port construction news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1PHOTO OF THE DAY: Argentina dredges its canals before El Niño
  2. 2Høj Nordic completes Schleswig-Holstein annual dredging
  3. 3Oceanside Harbor's channel dredging about to begin
  4. 4HERBOSCH-KIERE's Atlantis wraps up work at Dumping Area 42

Daily dredging and port construction news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free