Oceanside Harbor Navigational Dredging Moves Ahead

In its latest update on the Oceanside Harbor navigational dredging scheme, the USACE said that the contractor, CJW Construction, removed nearly 26,500 cubic yards of material from the harbor’s entrance channels from August 4 through 10. 

To date, CJW has dredged roughly 91,500 cubic yards of the 260,000 cubic yards designated for removal.

The Oceanside Harbor navigational dredging project is an annual project conducted to maintain the federal channels within Oceanside Harbor at their authorized federal depth and to provide safe navigation for the recreational, commercial and military vessels that use the channels.

Oceanside Harbor is one of four annual dredging projects conducted by the Los Angeles District.

Material dredged from the entrance channels is being placed along Oceanside’s beach. Placement of beach quality material along the shoreline is a beneficial byproduct of the maintenance dredging project.

CJW is currently discharging material just north of the Oceanside pier.

 

Share this article

Follow Dredging Today

Events>

<< Apr 2020 >>
MTWTFSS
30 31 1 2 3 4 5
6 7 8 9 10 11 12
13 14 15 16 17 18 19
20 21 22 23 24 25 26
27 28 29 30 1 2 3

Navingo Career Event 2020

The Navingo Career Event is Europe’s biggest career event for the maritime,…

read more >

Jobs>

Looking to fill a job opening?

By advertising your job here, on the homepage of DredgingToday.com, you'll reach countless professionals in the sector. For more information, click below....

apply

Dredging jobs in Abu Dhabi at NMDC

National Marine Dredging Company “NMDC” aims to be the largest dredging player in the Arab’s Gulf region...

apply

Looking to fill a job opening?

By advertising your job here, on the homepage of DredgingToday.com, you'll reach countless professionals in the sector. For more information, click below...

apply