Eight million cubic meters have been dug in the New Suez Canal project so far, the Armed Forces said in a statement.

The digging pace will be increased after the rest of the digging equipment get into action,” the statement said.

Forty-two companies and two battalions are taking part in the project, it indicated.

The new project aims to build a new canal parallel to the current one, with a total length of 72 kilometers.

Press Release, August 18, 2014

Share this article

Follow Dredging Today

Events>

<< Mar 2020 >>
MTWTFSS
24 25 26 27 28 29 1
2 3 4 5 6 7 8
9 10 11 12 13 14 15
16 17 18 19 20 21 22
23 24 25 26 27 28 29
30 31 1 2 3 4 5

Navingo Career Event 2020

The Navingo Career Event is Europe’s biggest career event for the maritime,…

read more >

Jobs>

Looking to fill a job opening?

By advertising your job here, on the homepage of DredgingToday.com, you'll reach countless professionals in the sector. For more information, click below...

apply

Dredging jobs in Abu Dhabi at NMDC

National Marine Dredging Company “NMDC” aims to be the largest dredging player in the Arab’s Gulf region...

apply

Looking to fill a job opening?

By advertising your job here, on the homepage of DredgingToday.com, you'll reach countless professionals in the sector. For more information, click below....

apply