Panama Canal Expansion Update – August 2014 (VIDEO)

The Panama Canal expansion project will double the capacity of the Panama Canal by 2015 by creating a new lane of traffic and allowing more and larger ships to transit.

The program consists of the construction of two new sets of locks – one on the Pacific and one on the Atlantic side of the Canal. Each lock will have three chambers and each chamber will have three water reutilization basins.

The program also entails the widening and deepening of existing navigational channels in Gatun Lake and the deepening of Culebra Cut.

In order to open a new 6.1 km-long access channel to connect the Pacific locks and the Culebra Cut, four dry excavation projects will be executed.

Related:

Panama Canal Expansion Program Update – July 2014

August 21, 2014

Share this article

Follow Dredging Today

Events>

<< Apr 2020 >>
MTWTFSS
30 31 1 2 3 4 5
6 7 8 9 10 11 12
13 14 15 16 17 18 19
20 21 22 23 24 25 26
27 28 29 30 1 2 3

Navingo Career Event 2020

The Navingo Career Event is Europe’s biggest career event for the maritime,…

read more >

Jobs>

Looking to fill a job opening?

By advertising your job here, on the homepage of DredgingToday.com, you'll reach countless professionals in the sector. For more information, click below....

apply

Looking to fill a job opening?

By advertising your job here, on the homepage of DredgingToday.com, you'll reach countless professionals in the sector. For more information, click below...

apply

Dredging jobs in Abu Dhabi at NMDC

National Marine Dredging Company “NMDC” aims to be the largest dredging player in the Arab’s Gulf region...

apply