The Netherlands: Building the Hard Seawall at Maasvlakte 2

Protect the newly sprayed-on land against the winter storms. That’s the Blockbuster. After the stormy season, the enormous crane will continue blocks in the new Maasvlakte sea defence.

To protect the land from the sea, Maasvlakte 2 will have a hard seawall that stretches over a length of 3.5 km along its northern edge. The hard seawall consists of a stony dune and a block dam. The stony dune is a sand dune with a top layer of fist-sized cobbles, similar to the natural cobble beaches found in France and England, which have proven to be extremely safe.

In front of this construction, there will be a dam of large concrete blocks in the sea that will serve as a breakwater. Around 17,000 concrete blocks from the Maasvlakte’s existing block dam will be recycled for this new dam. This both reduces waste and limits the amount of new material required for the dam.

Temporary protection from the storm

The foundation for the hard seawall is already in place. Not only has the sand bank been rainbowed on; a large number of cobbles have already been spread across the stony dune too. However, some terrible storms can blow in the autumn and winter, meaning that temporary measures are required to protect the cobbles. This has become the first big job for the Blockbuster, the enormous crane that was especially designed to place the largest rocks and concrete blocks in the Maasvlakte 2 seawall. By now, the crane is in position on the edge of the sea, along the outer rim of the new land.

It has started to apply temporary protection to the stony beach in preparation for the coming stormy season. The protection consists of heavy riprap and the same 40 ton concrete blocks that will soon be positioned with far more precision in the final version of the hard seawall. Once the temporary protection of the new land is in place, the Blockbuster can get cracking on the actual construction of the hard seawall.

Source: mv2, December 1, 2010

Share this article

Follow Dredging Today

One thought on “The Netherlands: Building the Hard Seawall at Maasvlakte 2”

Comments are closed.

Events>

<< Sep 2016 >>
MTWTFSS
29 30 31 1 2 3 4
5 6 7 8 9 10 11
12 13 14 15 16 17 18
19 20 21 22 23 24 25
26 27 28 29 30 1 2

Marine & Coastal Civil Engineering 2016

Marine & Coastal Civil Engineering 2016 is the UK’s leading event in presenting global solutions and innovative concepts to professionals…

read more >

Dredging for flood prevention and response, London

The September CEDA half-day seminar will focus on dredging in flood prevention and response: what can dredging do to reduce the risk…

read more >

MIDAS Final Meeting

This meeting will showcase the final results and outcomes arising from the past 3 years of MIDAS research. The meeting is open to all, but…

read more >

INNOVATION IN FLOOD RISK MANAGEMENT IN THE UK

This seminar will cover the benefits and approaches to innovation in flood risk management. This includes innovations in engagement with…

read more >

Jobs>

Design Engineer Standard Cutter Suction Dredgers

As a Design Engineer you will be involved in the concept, basic and detail design of Cutter Suction Dredgers...

apply

Hydrographic Surveyor

Gahagan & Bryant Associates, Inc. (GBA) is posting the following career opportunity in their Houston, TX and Baltimore, MD and Tampa, FL offices....

apply

Dredge Masters, Engineers and Superintendent\\\\\\\'s Urgently Required!

Flagship Management is working with a number of leading international marine and dredging organizations and require the following candidates for a range of global projects...

apply