Panama Canal Authority, GUPC Achieve Milestone Agreement

The Panama Canal Authority (ACP) and the consortium Groups Unidos por el Canal (GUPC) signed the variation incorporating to the original contract the agreement reached in March for completion of the Third Set of Locks project.

“What remains now is to continue working with the commitment to complete the Expansion which is currently at a 78% progress,” said ACP Administrator Jorge L. Quijano.

The Expansion Program registers an overall progress of 78%, while the new locks project is currently 73% complete.

The consortium GUPC is formed by Sacyr Vallehermoso, S.A., Impregilo, S.p.A., Jan de Nul Group and Constructora Urbana, S.A. (CUSA).

The parties signed in March a Memorandum of Understanding (MoU) establishing the framework for the completion of the Third Set of Locks project.

Press Release, August 4, 2014

Share this article

Follow Dredging Today

Events>

<< Oct 2019 >>
MTWTFSS
30 1 2 3 4 5 6
7 8 9 10 11 12 13
14 15 16 17 18 19 20
21 22 23 24 25 26 27
28 29 30 31 1 2 3

CEDA Dredging Days 2019

The conference is well-attended by professionals representing the entire cross-section of the dredging field…

read more >

2019 Western Dredging Association Gulf Coast Chapter Annual Meeting

The meeting will provide a forum for the exchange of information of interest to the dredging industry and its associates.

read more >

Jobs>

Looking to fill a job opening?

By advertising your job here, on the homepage of DredgingToday.com, you'll reach countless professionals in the sector. For more information, click below....

apply

Dredging jobs in Abu Dhabi at NMDC

National Marine Dredging Company “NMDC” aims to be the largest dredging player in the Arab’s Gulf region...

apply

Looking to fill a job opening?

By advertising your job here, on the homepage of DredgingToday.com, you'll reach countless professionals in the sector. For more information, click below...

apply