Dharanboodhoo Harbor development moves forward

Maldives Transport and Contracting Company (MTCC) today announced the latest update regarding the F. Dharanboodhoo Harbor development program.

MTCC

According to MTCC, work on the design and build of F. Dharanboodhoo Harbor is well underway, with an overall 50% project progress so far. 

MTCC photo

The installation works on precast concrete blocks required for quay wall construction have been completed.

Maintenance dredging works for the project is currently ongoing.

The project includes:

  • dredging and excavation operations of 46,600cbm;
  • construction of a 253m quay wall;
  • 410m breakwater;
  • 64m revetment;
  • installation of 2,500sqm of paved area and installation of harbor lights.

Total value of these works is MVR 38.2 million ($2.5 million).