North Lincolnshire flood defence work complete

People in South Ferriby are better protected from tidal surges and sea level rises following the completion of a £14 million flood defence in North Lincolnshire.

Environment Agency

The major investment reduces flood risk for 150 properties in the area, as well as 3,000 hectares of agricultural land and vital infrastructure. This includes the A1077 and the Scunthorpe to Grimsby railway line, which carries 20% of the UK’s freight.

The reduced risk is predicted to prevent £248 million of potential economic damage over the defences’ lifespan.

Starting in April 2019, the project has seen around 3 kilometres of new and raised defences built between Ferriby Sluice and South Ferriby village. That includes embankments, flood walls, de-mountable barriers and flood gates.

The new defences are now higher than the water level seen in the devastating tidal surge of December 2013. That means local communities are now protected from a similar event.

The height also takes account of climate change predictions up to 2050.

The improvements to the flood defences at South Ferriby are part of the ongoing investment in tidal flood risk management around the Humber.