Army Corps Deactivates Phase I Flood Fight (USA)

Water levels along the Mississippi River continue to drop, prompting the U.S. Army Corps of Engineers to deactivate Phase I flood fight inspections.

As a result of this deactivation, all permitted construction work near levees and floodwalls along or near the river may now resume.

The Corps activated phase I flood fight as a proactive measure on March 27, 2012, when the Mississippi River rose above 11 feet.

The levee patrols associated with phase I activation help ensure the Corps and the local levee authorities can respond quickly to problem areas that may develop along the levee system due to the elevated water levels.

In addition, restrictions were placed on all construction activity near the river levees and floodwalls in accordance with their respective permits.

[mappress]

Dredging Today Staff, April 17, 2012;