Sino-Myanmar Dredging Project Wrapped Up

Business & Finance

Sino-Myanmar Dredging Project Completed

On July 24, Zhenghua 29 46,000t semi-submersible barge loaded with six workboats, including Tianlin, Jinhangjun 405, Jinhangbo 48, Jinhangbo 49, CCCC Tongyun 1 and Yuanchang 8 started to return to China after several days’ welding and fixing.

With this, the channel dredging work of Sino-Myanmar Crude Oil Pipeline Project ended successfully.

The channel dredging work of Sino-Myanmar Crude Oil Pipeline Project started on September 26, 2011. The construction was full of twists and turns and even suspended for twice. However, with the unremitting efforts, the project department finally overcame all the difficulties and completed the construction on April 26, 2013, 35 days ahead of the schedule.

[mappress]

Press Release, August 14, 2013