USA: Port of Newport Dredging Completed

Port of Newport Dredging Completed

The Port of Newport has seen productive results from channel dredging at the NOAA MOC-P wharf this year.

From January 6 until February 21, 2014, the Army Corps of Engineers removed over 7,000 cubic yards of material from the upper channel near the turning basin.

Newport is budgeted for twenty-one days of dredging next season, and it is also possible that state funding will allow the Corps to concentrate even more on the upper channel and turning basin.

[mappress]

Press Release, March 17, 2014