The Tarpon Springs-based company, Florida Dredge and Dock, last week wrapped up the Sunrise Canal dredging program on schedule and budget.

The company completed dredging in six working days, said City Engineer Jim Bouquet.

Dredging area

This $150,000 dredging scheme, located in a residential portion of New Town off Flagler Avenue, included removal of approximately 25 truckloads of material from the canal.

Bouquet said that the contractor dredged the canal to five feet below the mean low water mark.

Dredging Today Staff, May 5, 2014

Share this article

Follow Dredging Today

Events>

<< Oct 2019 >>
MTWTFSS
30 1 2 3 4 5 6
7 8 9 10 11 12 13
14 15 16 17 18 19 20
21 22 23 24 25 26 27
28 29 30 31 1 2 3

CEDA Dredging Days 2019

The conference is well-attended by professionals representing the entire cross-section of the dredging field…

read more >

2019 Western Dredging Association Gulf Coast Chapter Annual Meeting

The meeting will provide a forum for the exchange of information of interest to the dredging industry and its associates.

read more >

Jobs>

Looking to fill a job opening?

By advertising your job here, on the homepage of DredgingToday.com, you'll reach countless professionals in the sector. For more information, click below...

apply

Looking to fill a job opening?

By advertising your job here, on the homepage of DredgingToday.com, you'll reach countless professionals in the sector. For more information, click below....

apply

Dredging jobs in Abu Dhabi at NMDC

National Marine Dredging Company “NMDC” aims to be the largest dredging player in the Arab’s Gulf region...

apply