Panama Canal Expansion Progress Rapidly

Currently at 93.1% completion, the Panama Canal Expansion Program continues to rapidly progress.

This month, the filling of the fourth phase of the Pacific Access Channel (PAC-4) began, bringing Culebra Cut one step closer to connecting with the new Pacific-facing locks.

The new channel is 6.1 kilometers long and 218 meters wide, and it is located 9 meters above the level of Miraflores Lake. This will be the channel Neo Panamax vessels take to bypass Miraflores Lake at the completion of the expansion.

The filling process is expected to take approximately 20 days to complete, as water levels rise between 0.5 and 1.0 meter per day. Once the area is filled, the condition of the dam will be tested and verified before removing the plug that separates the new access channel from the current.

According to Panama Canal Administrator. Jorge L Ouijano, the new Pacific Access Channel is nearly ready to accommodate the larger Neo Panamax vessels that will transit through the waterway.

Share this article

Follow Dredging Today

Events>

<< Mar 2020 >>
MTWTFSS
24 25 26 27 28 29 1
2 3 4 5 6 7 8
9 10 11 12 13 14 15
16 17 18 19 20 21 22
23 24 25 26 27 28 29
30 31 1 2 3 4 5

Navingo Career Event 2020

The Navingo Career Event is Europe’s biggest career event for the maritime,…

read more >

Jobs>

Looking to fill a job opening?

By advertising your job here, on the homepage of DredgingToday.com, you'll reach countless professionals in the sector. For more information, click below....

apply

Looking to fill a job opening?

By advertising your job here, on the homepage of DredgingToday.com, you'll reach countless professionals in the sector. For more information, click below...

apply

Dredging jobs in Abu Dhabi at NMDC

National Marine Dredging Company “NMDC” aims to be the largest dredging player in the Arab’s Gulf region...

apply