Another Milestone for Aberdeen Harbor Expansion Project

The largest accropode ever to have been produced by automated factory process has been successfully completed in Aberdeen.

The temporary building, which is 15 meters high and 120 meters long, has been specially constructed to support the £350 million Aberdeen Harbor Expansion Project, which is due for completion in 2020.

The facility is home to a carousel production system, which will be used to manufacture around 9,000 accropodes, that will be used as the outer armor for the north and south breakwaters.

The first 16m³ accropode – which was completed this week – is the largest to have been produced by an automated factory process.

Keith Young, Engineering Director, Aberdeen Harbor Board, said: “The new temporary facility uses the latest automated technology to ensure a high quality of construction is maintained through each accropode and that they are produced as efficiently as possible. We have taken care to engineer the new South Harbor to the highest standard, designing it to be protected from a 1-in-200-year storm.”

The commencement of production at the new facility represents another significant landmark reached in the expansion. Our principal contractor Dragados, is continuing construction on the north breakwater, with construction of the south breakwater due to start in June, and the accropodes will form a key part of this ongoing work,” added Keith Young.

The accropode production follows other significant steps forward at the South Harbor expansion, with dredging activities having resumed with the arrival of the hydraulic backhoe dredger ‘Goliath’ – one of the largest backhoe dredgers in the world.

The dredging operation will remove 2.2 million cubic meters of sediment to increase the water depth within the bay ahead of the construction of the quays over the next two years, and the subsequent development of world-class deep-water berthage.

In addition, the first caisson – one of the concrete ‘building blocks’ that will be used to start the closed-quay sections of the facility – has been constructed. The caisson, which is 50 meters long, 17 meters wide and 16 meters high, will be floated into position this summer after being transported to Aberdeen from the north of Spain.

 

Share this article

Follow Dredging Today

Events>

<< May 2018 >>
MTWTFSS
30 1 2 3 4 5 6
7 8 9 10 11 12 13
14 15 16 17 18 19 20
21 22 23 24 25 26 27
28 29 30 31 1 2 3

WEDA’s Dredging Summit & Expo ’18

The Dredging Summit & Expo ’18 is a technical conference organized by the Western Dredging Association (WEDA)…

read more >

State of the Coast Conference 2018

OC18 will consist of two and a half days of presentations by leading experts in concurrent sessions…

read more >

Ukrainian Port Forum (UPF) 2018

The Ukrainian Port Forum (UPF) is the flagship event on collaborative financing for port infrastructure development…

read more >

SEMINAR ON DREDGING AND RECLAMATION (THE NETHERLANDS)

This five-day course strives to provide an understanding through lectures by experts in the field and workshops, partly conducted on-site…

read more >

Jobs>

Looking to fill a job opening?

By advertising your job here, on the homepage of DredgingToday.com, you'll reach countless professionals in the sector. For more information, click below....

apply

Dredging jobs in Abu Dhabi at NMDC

National Marine Dredging Company “NMDC” aims to be the largest dredging player in the Arab’s Gulf region...

apply

Looking to fill a job opening?

By advertising your job here, on the homepage of DredgingToday.com, you'll reach countless professionals in the sector. For more information, click below...

apply