The Maldives Transport and Contracting Company Plc (MTCC) has just released the latest update on their S. Meedhoo harbor project.
According to their official statement, work is well underway the S. Meedhoo harbor upgrade scheme – with 60% overall project progress at the moment.
The project involves harbor basin’s dredging operations of 35,496cbm; channel entrance dredging of 22,500cbm; the construction of a 115m rock boulder breakwater; a 496m quay wall and 2,480qm paved area.
Overall scope of works for the project is valued at $2.3 million.
The equipment for the project, awarded to MTCC on 23rd June 2019, was subsequently mobilized on 18th September 2019.
Photo: MTCC
List of related news articles
-
Posted: 27 days ago
Isdhoo Harbor development moves forward
The L. Isdhoo Harbor development program is moving ahead according to schedule, Maldives Transport a...
Posted: 27 days ago -
Posted: 6 days ago
Work on Ihavandhoo Harbor moves ahead
Development work of Ha. Ihavandhoo Harbor is well underway, with overall 35% project progress to dat...
Posted: 6 days ago -
Posted: 11 days ago
Dharanboodhoo works move ahead
Maldives Transport and Contracting Company (MTCC) today released the latest update on their F. Dhara...
Posted: 11 days ago -
Posted: about 1 month ago
Nellaidhoo Harbor development moves ahead
Work on the Hdh. Nellaidhoo Harbor Development Project is well underway, the Maldives Transport and ...
Posted: about 1 month ago