Veyvah Harbor development in full swing

Work on M. Veyvah Harbor is well underway, with overall 39% project progress, Maldives Transport and Contracting Company (MTCC) reported today.

MTCC

The construction of a concrete wall and the installation of mooring rings are currently ongoing, with 39% and 20% completion respectively.

The M. Veyvah Harbor project includes:

  • dredging and excavation operations of 60,839cbm;
  • construction of a 350m breakwater;
  • a 35m revetment;
  • a 380m quay wall;
  • 1,880sqm of paved area and installation of street lights.
MTCC photo

The estimated value of the project is $3.2 million.

According to MTCC, the Veyvah contract was awarded on 27th August 2019.