Phase II of Boston Harbor dredging wraps up

USACE and Massachusetts Port Authority (Massport) have announced that Phase II of the Boston Harbor Dredging Project is now complete – ahead of schedule by nearly one full year.

Cashman

USACE, partnering with Cashman Dredging Inc. and Dutra Group, have worked 365 days a year, 24 hours a day, since July 2018 to complete this second of three deepening contracts to deepen the Harbor.

The project is a $350 million partnership between USACE, the Commonwealth of Massachusetts, and Massport. 

The first contract, maintenance dredging of the inner harbor and construction of a Confined Aquatic Disposal cell, was completed in December of 2017.

The current and second contract, deepening of the main ship channels, began in July 2018 to accommodate the large container vessels calling today and in the future. 

The third and final contract, which will remove hard rock to complete the deepening, is scheduled to be awarded in January 2021.

 “We look forward to awarding the final phase of the Boston Harbor Deepening Project,” said Col. John A. Atilano II, Commander, U.S. Army Corps of Engineers, New England District.

“Our partnership with Massport and all of our stakeholders has made this project a success to date, allowing us to start the final phase almost a year ahead of schedule. The ability for larger vessels to call on Boston is critical to New England’s economy and supports USACE’s core navigation mission.”

Through this project’s second phase, the crews were deepening the Outer Harbor Channel, from 40 to 51 feet; the Main Shipping Channel, from 40 to 47 feet; and the Reserve Channel, where Conley Container Terminal is located, from 40 to 47 feet.

Additionally, USACE was able to contribute to expanding the Harbor’s Turning Basin to 1,725 feet, which is essential to welcome larger ships.

Currently, Conley is able to handle ships carrying 10,000 TEUs (twenty-foot equivalent units) – this project will allow Conley to handle up to 12-14,000 TEU vessels.