Royal BAM Half-Year Results

Royal BAM Group today presented the most important key figures of the first half-year 2018, reporting the 1H18 ...

read more →

August Update on IJmuiden Works

During this month, OpenIJ will – under the New IJmuiden Sea Lock project – continue working on the ...

read more →

New End Date for IJmuiden Works

The construction of the new sea lock in IJmuiden has been delayed by 27 months, reported the Port of Amsterdam. ...

read more →

IJmuiden July Update Released

Despite the delay in the construction of the IJmuiden sea lock reported this month, activities are continuing ...

read more →

IJmuiden Lock Completion in 2022

Dutch Minister of Infrastructure and Water Management, Cora van Nieuwenhuizen, informed yesterday the Dutch House ...

read more →

IJmuiden Lock - June Update

The construction of the lock gate chamber of the outer head, which is part of the IJmuiden Sea Lock Project, is ...

read more →

The Middle Lock Closure Ends

The Port of Amsterdam recently released the latest update on the IJmuiden Sea Lock Project. In its update for May, ...

read more →

Highlights of the Week

Dredging Today brings you an overview of the most popular stories from the past week (April 9-15, 2018).   ...

read more →

IJmuiden Project Takes Shape

The most visible construction work at the new IJmuiden sea lock this month will be at the lock gate chambers of the ...

read more →

IJmuiden Construction Continues

At the end of last year, BAM and VolkerWessels reported disappointing financial results related to the new sea lock ...

read more →

IJmuiden Lock– February Update

Construction works continued this month on the new sea lock at IJmuiden, the Netherlands, with the new control ...

read more →

IJmuiden Lock– January Update

The construction of the new sea lock at IJmuiden, the Netherlands, continued throughout January with the works on ...

read more →

IJmuiden Lock – December Update

This month, work will continue on the construction of the gate chambers for the new sea lock at IJmuiden, the ...

read more →

Cost Overrun at the IJmuiden

Based on the latest available information, Royal BAM Group expects a considerable project loss in 2017 on the sea ...

read more →

IJmuiden Lock November Update

Concrete pouring operations for the floors of the new sea lock at IJmuiden continue throughout this month as well ...

read more →

APT Opens Office in IJmuiden

The APT Global group today announced the opening of a new office in the Netherlands. The new office, located at ...

read more →

IJmuiden Lock October Update

The start of the construction of the IJmuiden New Sea Lock control building and the relocation of the two waiting ...

read more →

IJmuiden Lock September Update

Construction work on the IJmuiden Sea Lock Project has continued during the summer holidays, reports the Port of ...

read more →

IJmuiden Sea Lock Project Update

The Port of Amsterdam today released an update on the new sea lock project at IJmuiden, the Netherlands. This ...

read more →

IJmuiden Sea Lock Agreement

The amounts of the financial contributions to the new sea lock at IJmuiden have been finalized and agreed upon by ...

read more →

Solar Powerpack Passes the Test

In cooperation with Dutch dredging contractor Royal Boskalis Westminster N.V., HollandMT has successfully completed ...

read more →